Installation Procedure
NOTICE
The axle jack may only be mounted in a suitable lift. The load capacity of the axle
jack must not exceed 2/3 of the lift load capacity.
1 Lift the axle jack out of the packaging and place it at the desired height on
suitable supports between the runways.
NOTICE
The support plate and frame may only be lifted if the axle jack is tied together.
Otherwise, the support plate is not supported by the cylinder and the axle jack will
crash when releasing the safety stop.
2 Mount the side pieces including roller axles with rollers in the holes so that the
axle jack is at the desired height. There are multiple choices for flange and roller
axle mounting. The height can be varied by 12.5 mm by turning the black
extensions in the axle jack (Fig. A).
3 Oil the roller axles while in mounted position.
4 Position in the guide rail of the runway or in the pit.
5 To secure against collapsing, drill an
8.5 hole on both sides directly outside
the frame and mount with a bolt and nut (Fig. B).
6 Check all screws and nuts for tightness. Retighten if necessary.
CAUTION
Risk of personal injury and property damage
With danger of derailment additional safety measures are needed, especially
with lift types as shown in Fig. C (synchronisation of runways!).
The safety technician must decide about the necessary safety measures for
each individual case.