Full Height Turnstile MPT-132
Assembly and installation
29
NOTE!
Before starting assembly, establish whether the
cage half is to be right or left entry. See Fig. 9.
If code card reader, buttons or columns are pre-
mounted on the cage half, they are important for
setup.
5.4.1
Mounting full height turnstile on the foundation
NOTE!
The foundation must have hardened off.
Foundation and empty conduits must be tested pri-
or to commencing assembly.
The full height turnstile is mounted to the founda-
tion by 6 composite anchors. The mounting materi-
al is included in the delivery.
Fig. 10: Drilling jig
1. Make the bore holes as per the drilling plan (see Page 25,
Fig. 4). Use the drilling jig supplied.
2. Carefully remove any sand and swarf from the bore holes and
their immediate vicinity.
3. Set the anchor bolts supplied as shown on the enclosed de-
scription and allow hardening.
Fig. 11: Power and control cables