Lucent Technologies Lineage
®
2000 ECS/GPS Battery Plant J85500G-2
3 - 22 Engineering, Planning and Ordering
Issue 6 May 1999
Thermal
(slope/step)
compensation
The thermal compensation feature is available as an option.
Is Thermal Compensation feature required? _____(yes or no)
Controller
Options
The engineering of the controller features involves orderable
circuit packs and field-movable jumper straps or DIP switches.
Circuit Packs: Circuit pack options for the ECS controller are
listed on the J85500G-2 drawing and in the Controller Product
Manual. Circuit pack options for the Galaxy controller are listed
on the Galaxy controller drawing J85501F-1 and in the Galaxy
controller Product Manual.
DIP Switches and Jumper Straps: Certain controller features
must be set during the installation process if requirements differ
from the standard factory settings. The engineering process must
provide the necessary instructions to the installer for the
controller set-up. Refer to the J85501D-2 or J85501F-1
controller drawing and the Controller Manual for details.
Alarm System
Interface
The standard ECS and Galaxy controllers are equipped with
connection points for a variety of battery plant alarms. The
wiring from the controller alarm points to the local and remote
reporting alarm systems, however, is NOT provided with the
battery plant. Such wiring must be compatible in gauge and type
with the terminal blocks provided on the controller circuit packs,
as detailed in the Controller Manual.
Earthquake
Bracing
The earthquake ratings for the standard ECS battery plant are
given below:
•
Initial bay: Zone 4, upper floors, per NEBS TR-EOP-00063
•
Supplementary bay with 6 rectifiers and distribution: Zone
4, upper floors
•
Supplementary bay with 1 string VR batteries: Zone 4,
upper floors
•
Supplementary bay with 2 strings VR batteries: Zone 2,
ground level (not recommended for Zone 4 applications)
A supplementary bay equipped with two strings of VR batteries
should be junctioned to adjacent frameworks when possible and
should be tied to the building or vault wall for additional rigidity
in Zone 3 applications. The supplementary bay equipped with