LEFT
0"
MINIMUM
TOP
6"
MINIMUM
BOTTOM
0"
MINIMUM
FRONT
6"
MINIMUM
RIGHT
0" MINIMUM
1/4"MINIMUM CLEARANCE
AROUND HOT WATER PIPES
1" MINIMUM CLEARANCE
AROUND VENT PIPE
OPEN DOOR
DIR #2000534544 00
Figure 1-2 Alcove Installation - Minimum Required Clearances
LEFT
0"
MINIMUM
TOP
6"
MINIMUM
6"
6"
BOTTOM
0"
MINIMUM
FRONT
6"
MINIMUM
1/4"MINIMUM CLEARANCE
AROUND HOT WATER PIPES
VENTING*
OPENING
VENTING*
OPENING
1" MINIMUM CLEARANCE
AROUND VENT PIPE
DIR #2000534543 00
Figure 1-1 Closet Installation - Minimum Required Clearances
WARNING
For closet installations, CPVC,
polypropylene, or stainless steel
vent material MUST BE used in
a closet structure due to elevated
temperatures. Failure to follow
this warning could result in fire,
personal injury, or death.
Note:
Service clearances are recommendations only.
Note:
Service clearances are recommendations only.
WARNING
For alcove installations, CPVC,
polypropylene, or stainless steel
vent material MUST BE used in
an alcove structure due to elevated
temperatures. Failure to follow
this warning could result in fire,
personal injury, or death.
8
1
Determine boiler location
Minimum Clearances to Combustible
Materials
Location
Clearances
From Top of the Unit
6"
From Front of the Unit
6"
From Flue or Vent Connector
in any Direction
1"
From Back of the Unit
0"
From the Left Side of the Unit
0"
From the Right Side of the Unit
0"
Type of Floor - Combustible
Installation & Service Manual