User Manual
Hipulse - Single Phase ‘1+N’ UPS System
130 kVA - 110V
14
3.1.2
Cable rating
NOMINAL CURRENT (Amps)
3 Phase Input Mains with full
battery re-charge
(less 5% for 12 pulse)
1 Phase Output at full load
Battery at minimum
Battery Voltage
UPS
Rating
(kVA)
380V
400V
415V
110V
115V
120V
380V
400V
415V
30
63
60
58
272
260
250
83
80
77.5
40
84
80
77
364
349
334
110
106
103
50
105
100
96
454
434
416
137
133
129
60
126
119
115
545
521
500
164
159
155
80
165
157
151
727
695
666
219
213
206
120
245
233
223
1090
1043
1000
329
319
310
130
259
247
238
1181
1130
1083
357
346
336
150
300
285
275
1363
1304
1250
412
399
387
Table 3-1 UPS Module cabinet power cable rating
3.1.3
General Notes
The following are guidelines only and superseded by local regulations and codes of
practice where applicable:
1. The neutral conductor should be sized same as the output/ bypass current.
2. The earth conductor should be sized for carrying fault current for atleast 3 to 5
seconds or as guided by local electrical rules.
3. Consideration should be given to the use of paralleled smaller cables for heavy
currents, as this can ease installation considerably.
4. When sizing battery cables, a maximum volt drop of 3V d.c. is permissible at the
current ratings given in Table 3-1.
3.1.4
Cable Connections
The rectifier input, bypass, output and battery power cables (all require lug type
terminations) and are connected to busbars situated below the power isolator
switches - as shown in figure 3.1 for 80kVA and fig 3.2 for 120 /160/ 200kVA.
A terminal block X3 is used for connecting the control cables to the battery circuit
breaker and a second terminal block X4 is used for the external emergency stop
facility, external OFF inverter, ext. Bypass, etc. these are female spade type
connections (Fast-on 6.3 x 0.8) and are described later in Section 3.2
3.1.5
Safety earth
The safety earth busbar is located between the Bypass and Output power supply
connections as shown in the figure 3.1. The safety earth cable must be connected to
the earth busbar and bonded to each cabinet in the system.
All cabinets and cable trunking should be earthed in accordance with local
regulations.
Содержание 130 kVA
Страница 2: ...User Manual Hipulse Single Phase 1 N UPS System 130 kVA 110V...
Страница 4: ...User Manual Hipulse Single Phase 1 N UPS System 130 kVA 110V...
Страница 6: ...User Manual Hipulse Single Phase 1 N UPS System 130 kVA 110V...
Страница 8: ...User Manual Hipulse Single Phase 1 N UPS System 130 kVA 110V...
Страница 10: ...User Manual Hipulse Single Phase 1 N UPS System 130 kVA 110V...
Страница 12: ...User Manual Hipulse Single Phase 1 N UPS System 130 kVA 110V...
Страница 14: ...User Manual Hipulse Single Phase 1 N UPS System 130 kVA 110V...
Страница 16: ...User Manual Hipulse Single Phase 1 N UPS System 130 kVA 110V...
Страница 18: ...User Manual Hipulse Single Phase 1 N UPS System 130 kVA 110V...
Страница 20: ...User Manual Hipulse Single Phase 1 N UPS System 130 kVA 110V...
Страница 26: ...User Manual Hipulse Single Phase 1 N UPS System 130 kVA 110V 6...
Страница 42: ...User Manual Hipulse Single Phase 1 N UPS System 130 kVA 110V 22...
Страница 66: ...User Manual Hipulse Single Phase 1 N UPS System 130 kVA 110V 46...
Страница 82: ...User Manual Hipulse Single Phase 1 N UPS System 130 kVA 110V 62...
Страница 96: ...User Manual Hipulse Single Phase 1 N UPS System 130 kVA 110V 76...
Страница 97: ...User Manual Hipulse Single Phase 1 N UPS System 130 kVA 110V 77...
Страница 98: ...User Manual Hipulse Single Phase 1 N UPS System 130 kVA 110V 78...