Normal procedure for 1 phase 240V
A.
Installation Completion of AC module on Roof
*Take out bar code sticker of all AC modules to register in monitoring system [Enervu]
B. Circuit breaker reset of AC module.
C. Plug in Gateway to outlet near to circuit breaker.
D. Checking the status LED Lamp of the Gateway
3 Lamps ON ”Green” [Power, PLC, WLAN]
: Max. 1 Minute.
E.
Installer Mode
In APP
F.
MAC address list
In APP
Adding & registration for AC Module : Real time sync
* After adding & registration, The Gateway automatically will recognize installed AC modules and It takes 5 seconds per
each AC module. When Gateway recognizes AC modules the LED color of PLC(No.7) will be Orange.
G. AC module status
In APP
Normal or abnormal condition
*Information on AC module through Gateway will be updated by every 15 minutes regardless normal or abnormal. If you
find abnormal AC module in APP, you have to clear error message and wait
Max.15 minutes again.
H.
Grid Configuration [Option]
In APP
Default “
Single phase 240V
”
*Only for 3 phase 208V.
I.
System configuration
In APP
It is
mandatory
to connect web server.
*Necessary procedure for Web server
*Take out bar code sticker of Gateway to register in monitoring system.
J. Sign In Enervu webpage for monitoring Gateway:
*Register bar code stickers of AC module and Gateway.
Procedure from B to F will be completed within 15 minutes, if not, the AC module will be sleep mode.
In case of sleep mode[For power saving], to wake up AC modules, you require to reset circuit breaker of AC module.
The initial operation of AC module will be started within 1 minutes after switch on of Circuit breaker. It is not affected to operating status
of AC modules during a setting APP. These are different mechanism.
Do not inform the App [Enervu] for setting monitoring to end customer, it can occur the system faulty, if customer change the setting.
This is only for the installation purpose. If they request the monitoring tool for AC module, we request to inform to end customer the web
address for Enervu,
Содержание MonoX ACe
Страница 1: ...Installer Guide Hardware and software for LGE Ace ...
Страница 3: ...AC Module Installation Guide Specification of AC Module ...
Страница 4: ...AC Module Installation Guide Specification of AC Module ...
Страница 5: ...AC Module Installation Guide Specification of AC Module ...
Страница 8: ...AC Module Installation Guide Specification of EnerBox ...
Страница 9: ...AC Module Installation Guide The connection method of Enerbox ...
Страница 19: ...AC Module Installation Guide APP and Web setting ...
Страница 31: ...Entering the Installer Mode Press for 2 3 sec 1 1 Press the title bar for 2 3 seconds to enter installer mode ...
Страница 36: ...EnerVu Web Configuration http enervu lg solar com ...
Страница 37: ... Appendix 1 Replacement procedure of malfunction Gateway ...
Страница 38: ... Appendix 2 Replacement procedure of malfunction AC module ...
Страница 39: ... Appendix 3 PLC Powerline Communication Issues ...
Страница 40: ... Appendix 3 PLC Powerline Communication Issues ...