• Preparation of Piping
6. Connecting Pipes to the Indoor Unit
Main cause of gas leakage is defect in flaring
work. Carry out correct flaring work in the following
procedure.
1) Cut the pipes and the cable.
■
Use the accessory piping kit or the pipes pur-
chased locally.
■
Measure the distance between the indoor and
the outdoor unit.
■
Cut the pipes a little longer than measured dis-
tance.
■
Cut the cable 1.5m longer than the pipe length.
2) Burrs removal
■
Completely remove all burrs from the cut cross
section of pipe/tube.
■
Put the end of the copper tube/pipe to downward
direction as you remove burrs in order to avoid
to let burrs drop in the tubing.
3) Putting nut on
■
Remove flare nuts attached to indoor and out-
door units, than put them on pipe/tube having
completed burr removal.
(Not possible to put them on after flaring work)
4) Flaring work
■
Carry out flaring work using flaring tool as
shown below.
Firmly hold copper tube in a bar(or die) as indicat-
ed dimension in the table above.
5) Check
■
Compare the flared work with figure below.
■
If flare is noted to be defective, cut off the flared
section and do flaring work again.
Copper
tube
90
°
Slanted Uneven Rough
Pipe
Reamer
Point down
Flare nut
Copper tube
Bar
Copper pipe
Clamp handle
Red arrow mark
Cone
Yoke
Handle
Bar
"A"
Inclined
Inside is shining without scratches
Smooth all round
Even length
all round
Surface
damaged
Cracked Uneven
thickness
= Improper flaring =
Outside diameter
A
mm
inch
mm
Ø9.52
3/8
0.5~0.8
Ø15.88
5/8
0.8~1.0
Ø19.05
3/4
1.0~1.3
Содержание LT-B2421CL
Страница 13: ...Wiring Diagram 1 Indoor Unit 1 COOLING ONLY 2 HEAT PUMP 13 ...
Страница 46: ... 46 Electronic control device MAIN P C B ASM ...
Страница 47: ...Schematic Diagram 47 ...
Страница 50: ... 50 130911 3 130911 1 130911 2 152302 146812 267110 2 140570 359011 346810 135312 137213 267110 1 ...
Страница 86: ...P No 3828A30023K December 2000 Printed in Korea P No 3828A20023K December 2000 Printed in Korea ...