COMMISSIONING
• Check the data on micro inverter and verify compliance
of these data with grid data
• Peel the label with Serial number and attach it to the
matrix in the same order as they are installed.
• When conducting the checks, ensure that the main AC
disconnector switch (downstream from the system) and
any other possible isolation switches are switched off
position
• Ensure that all conductors and protective grounding
points are connected
• Switch on the main AC disconnector switch
(downstream from the system) and any other possible
isolation switches
• Proceed with configuration of Gateway. Details are
described in Gateway User Manual.
Commissioning should be done by technically qualified personal.
Connecting cable output AC and DC voltage input cables
should be carried out in accordance with the manufacturer's
instructions (AMPHENOL).
4 Commissioning
4.1 Preliminary checks
4.2 Sequence of operations
• Check the position of all connection cables and the
tightness of all nuts and terminals
• Check the micro inverter is firmly mounted
• Ensure that all electrical safeguards have been correctly
installed
• Ensure that the complete system has been checked,
tested and approved in accordance with the local
standards and codes