7 Commissioning
Before switching on
EDK82ZMFBC-001 DE/EN/FR 7.0
54
H1inbet-INB_01_warn
7
Commissioning
Before switching on
Commissioning depends on the device combination (bus-I/O and fieldbus function
module). The commissioning procedure is described in the documentation on the fieldbus
system and the frequency inverter.
Switch position
1
ON
2 3
4
5
ON
OFF
Note!
ƒ
Make sure to set the DIP switch and C0034 to the same range, otherwise
the analog input signal at X3/8 will be interpreted incorrectly by the basic
device.
ƒ
If a setpoint potentionmeter is supplied internally via X3/9, make sure to
set the DIP switch to the voltage range 0 ... 5 V. Otherwise it will be
impossible to cover the entire speed range.
Signal at X3/8
Switch position
C0034
1
2
3
4
5
0 ... 5V
OFF
OFF
ON
OFF
OFF
0
0 ... 10 V (Lenze setting)
OFF
OFF
ON
OFF
ON
0
0 ... 20 mA
OFF
OFF
ON
ON
OFF
0
4 ... 20 mA
OFF
OFF
ON
ON
OFF
1
4 ... 20 mA (open-circuit monitored)
OFF
OFF
ON
ON
OFF
3
-10 ... +10 V
ON
ON
OFF
OFF
OFF
2