background image

 

EPS-2XPB-SG-DPMS 

Larson Electronics, LLC

 

 Phone: (800) 369-6671 

 Fax: (903) 498-3364 

  www.larsonelectronics.com 

1

 of 

2

 

EPS-2XPB-SG-DPMS OPERATION MANUAL 

Explosion Proof Double Push Button Switch 

READ THIS SHEET CAREFULLY BEFORE BEGINNING INSTALLATION. 

CAUTION

: Before installing, make sure you are compliant with area classifications, failure to do so may result in bodily 

injury, death and property damage. Do not attempt installation until you are familiar with the following procedures. All 
installation must comply with the applicable Electrical Code.  Make sure that the circuit is De-energized before starting 
installation or maintenance. Verify that the installation is grounded. Failure to ground will create electrical shock hazards, 
which can cause serious injury and or death. 

Important: 

Please read these instructions carefully before installing or 

maintaining this equipment. Good electrical practices should be followed at all times and this data should be used as a 
guide only. 

ENCLOSURE MOUNTING INSTALLATION:

 

If you have received fully assembled enclosure with factory installed devices, just follow the instructions and warnings 
below for installing and wiring the enclosure. 

The mounting location must be flat and provide proper clearance, rigidity and strength to support the enclosure and all 
contained devices. 

Securely fasten the enclosure to the mounting location.  Install sealing fittings, cable glands, unions and/or conduit, using 
an approved electrical conducting type lubricant on the threads.  The conduit thread connections must be tapered pipe 
thread conforming to ANSI B1.20.1.  A minimum of (5) full threads engagement is required for all conduit connections. 
Conduit sealing fittings must be installed within 18 inches of the enclosure.  Sealing fittings must be approved for the 
specific hazardous location where the enclosure is used.  All unused conduit openings must be plugged using close-up 
plugs.  Plugs must be tightly installed with a minimum engagement of (5) full threads. 

▲ Inspect and clean the machined flange flame joint surfaces of both the cover and the box.  Surfaces must be smooth, 
free of nicks, scratches, dirt or any foreign particle build-up that would prevent a proper seal.  Surfaces must seat fully 
against each other to provide a proper explosion-proof joint.  Clean surfaces by wiping with a clean, lint-free cloth. 

Apply a light coating of lubricant to flange surfaces and close the cover.  Tighten all cover bolts.  Use only those bolts 
supplied with the enclosure.  Check the bolted joint with a .0015 thick feeler gauge.  The gauge must not enter the joint 
more than 1/8” at any point. 

NOTE: 

Loose bolts or an improper joint can result in an explosion, creating a potential for 

personal injury and property damage. 

NOTE: If installing a breather and/or a drain, make certain they are suitable for the specific hazardous location where 
they are to be used.  Some drains/breathers may not comply with Nema 3 & 4 standards.  Also, provide a protective 
covering to shield the breather and drain during hose-down operations. 

Wire according to the diagrams on the switches. The factory installed pushbuttons in cover is set up to interface with 
the switches, once the cover was installed on the box. 

IMPORTANT: 

This enclosure and device 

must 

be installed by trained, qualified and competent personnel. Installation 

must 

comply with local, state and national regulations, as well as safety practices for this type of equipment. 

WARNING: 

Electrical power 

must 

be 

OFF 

during installation, or performing any maintenance. 

Disconnect 

primary power

source and 

lock out

Отзывы: