page 4
P 800.521.2546 F 269.381.3455 www.landscapeforms.com
7. Connect the Weather Pak connectors
attached to the solar panel and the
power unit controller.
8. Plug the luminaire into the LED driv-
er. Match the gray to the red, and the
black to the black.
Note: On units with two luminaires the
wiring is as follows:
A. Connect the Gray wire from
luminaire 1 to the Red wire of the
LED driver
B. Connect the Gray wire from
luminaire 2 to the Black wire of
luminaire 1
C. Connect the Black wire from
luminaire 2 to the Black wire of
the LED driver.
All electrical connections are complete at
this point.
9. Switch the battery disconnect to the
On position.
10. Before re-installing power module lid
(removed in Step 1), complete system
test as follows:
Press the “test” button on the Morn-
ingStar control. At this point the lumi-
naire(s) should be lit.
11. After completion of test procedure,
secure power module lid using six
#10-32 fasteners.
The installation process is now complete.
USE EXTREME CAUTION WHEN INSTALLING
BATTERY HARNESS. ALWAYS WEAR INSULATING
GLOVES WHEN CONNECTING BATTERIES.
Kaleidoscope® smart shelter installation and maintenance manual
Installation