Installation and Operating Instructions 

 

Copyright © 2019 Labkotec Oy 

5/14 

We reserve the right for changes without notice 

2.1 

Cabling when using cable junction box 

If the sensor cable must be extended or there is need for equipotential 
grounding,  it  can  be  done  with  the  cable  junction  box.  The  cabling 
between the SET-1000 control unit and the junction box should be done 
with a shielded twisted pair instrument cable. 

LJB2  junction  box  enables  cable  extension  in  potentially  explosive 
atmospheres. 

In  examples  in  figure  4  the  shields  and  excess  wires  have  been 
connected to the same point in galvanic contact with metallic frame of 
the junction box. This point can be connected to equipotential ground 
thru the ground terminal. Other components of the system that need to 
be grounded can also be connected to the same ground terminal. 

The  wire  used  for  equipotential  grounding  must  be  min.  2.5  mm² 
mechanically  protected  or,  when  not  protected,  the  minimum  cross 
section is 4 mm². 

Please make sure, that the cable  between SET-1000  and the  sensor 
does not exceed maximum connection values 

– see appendix 2. 

Detailed  cabling  instructions  can  be  found  in  the  instructions  of 
particular Labkotec SET sensors. 

 

 

Figure  4. Level  sensor  cabling  with  a  junction  box  for  cable 
extension. 

Junction  box  of  type  LJB2  include  light  alloy  parts.  When  installing  in 
explosive  atmosphere,  make  sure,  that  the  junction  box  is  located  so, 
that  it  can  not  be  mechanically  damaged  or  it  will  not  be  exposed  to 
external impacts, friction etc. causing ignition of sparks. 

Make sure, that the junction box is closed properly. 

Содержание SET-1000 12 VDC

Страница 1: ...D Tel 358 29 006 260 Fax 358 29 006 1260 24 9 2019 Internet www labkotec fi D15648_E 2 1 14 Copyright 2019 Labkotec Oy We reserve the right for changes without notice SET 1000 12 VDC Level switch for...

Страница 2: ...able junction box 5 2 2 Cabling when using cable joint 6 3 OPERATION AND SETTINGS 7 3 1 Operation 7 3 2 Altering settings 8 4 TROUBLE SHOOTING 10 5 REPAIR AND SERVICE 11 6 SAFETY INSTRUCTIONS 11 APPEN...

Страница 3: ...er alarms level control and alarms in oil sand and grease separators The LED indicators push buttons and interfaces of the device are described in figure 1 Figure 1 SET 1000 level switch features SET...

Страница 4: ...t cover The connectors of the external conductors are isolated by separating plates The plates must not be removed The plate covering the connectors must be installed back after executing cable connec...

Страница 5: ...to equipotential ground thru the ground terminal Other components of the system that need to be grounded can also be connected to the same ground terminal The wire used for equipotential grounding mu...

Страница 6: ...cable between SET 1000 control unit and the sensor do not exceed the maximum allowed electrical parameters see appendix 1 Technical data IP rating of the cable joint is IP68 Make sure that the cable j...

Страница 7: ...t a representative of the manufacturer Normal mode no alarms The level in the tank is below the sensor Mains LED indicator is on Other LED indicators are off Relays 1 and 2 are energized High level al...

Страница 8: ...e it is already in alarm status When the Test push button is released The device returns without delay to the preceding status Fault alarm on When pressing the Test push button The device does not rea...

Страница 9: ...will be on and relays de energize when the liquid level is above the sensor s trigger level high level mode OPERATIONAL DELAY SETTING DELAY Switch S2 is used to set the operational delay of the device...

Страница 10: ...easure the voltage separately between the poles 10 and 11 The voltages should be between 10 3 11 8 V 3 If the voltages are correct measure the sensor current Do as follows 3 1 Disconnect sensor s wire...

Страница 11: ...e atmosphere Sensors connected to it may be installed in explosive atmosphere zone 0 1 or 2 In case of installations in explosive atmospheres the national requirements and relevant standards as IEC EN...

Страница 12: ...uts Two potential free relay outputs 250 V 5 A 100 VA Operational delay 5 sec or 30 sec Relays de energize at trigger point Operation mode selectable for increasing or decreasing level Electrical safe...

Страница 13: ...0 15 mH 0 5 mH 1 0 mH 2 0 mH 5 0 mH Lo Ro 116 5 H IIC and 466 H IIB Table 2 Electrical parameters Maximum length of the sensor cable is determined by the resistance max 75 and other electrical parame...

Страница 14: ......

Отзывы: