On continuous pilot ignition models (JVT), if the

water temperature is below the limit setting, the
ignition module opens the main gas valve, and the
main burners ignite.

Operation will continue on all ignition systems

until either the wall setting thermostat is satisfied or
the high-limit thermostat opens. The burners and pilot
(on JVS models) shut-off and the pump relay turns off
the pump. The damper activator rotates the damper
blade to the closed position and the indicator light
goes off.

When the room temperature falls below the wall

thermostat setting, the cycle repeats.

Note: When equipped with a pump delay option,

the pump runs for a short time after the burners turn
off and the damper closes.

7.2 Start-up

7.2.1 Filling the System

NOTE:

 It is strongly recommended that the system be

cleaned and flushed to remove scale, oil, paste, flux,
etc., before the system is filled.

It is 

crucial

 to the efficient operation of the

system that all air be removed from the circuit. For
this reason, an air scoop and vent should be located
close to the boiler outlet, and there should be a
minimum distance between cold water feed and
system purge valve.
1.

When the system has been completely installed,
close all air vents and open the makeup water
valve. Allow the circuit to fill slowly.

2.

Adjust the pressure to provide a minimum of 12
psi (82.7kPa) at the highest point in the circuit. If
a pressure regulator is also installed in the line,
adjust it to the same pressure.

3.

Close all gate valves. Purge one circuit at a time
as follows:
a.

Open one circuit drain valve and let water
drain out for at least 5 minutes. Be certain
there are no air bubbles visible in the water
stream before closing the drain valve.

b.

Repeat this procedure for each circuit.

4.

Open all gate valves after all circuits have been
purged.

5.

Run the system circulating pump for a minimum
of 30 minutes with the boiler shut off.

6.

Open all strainers in the system, and check for
debris.

7.

Recheck all air vents as described in Step 3 above.

8.

Some expansion tanks require visual inspection
of liquid level. If necessary, inspect the liquid
level in the expansion tank. With the system
full of water, and under normal operating
pressure, to ensure proper water level in the
expansion tank.

9.

Start up boiler according to the procedures
described in Section 7 and operate the system,

including the pump, boiler, and radiation units,
for one hour.

10.

Recheck the water level in the expansion tank,
if necessary. If it exceeds ½ of the volume of
the tank, open the tank drain and reduce the
water level.

11.

Shut down the entire system, and vent all
radiation units and high points in the system.

12.

Close the water makeup valve and check the strainer
in the pressure reducing valve for sediment or
debris. Reopen the water makeup valve.

13.

Verify system pressure with the boiler pressure
gauge before beginning regular operation.

14.

Within 3 days of start-up, recheck and bleed all
air vents and the expansion tank using these
instructions.

15.

In systems piped with cross-linked polyethylene
tubng (PEX) it is essential that all air is purged
from all zones in the system to prevent PEX
tubing failure.

7.2.2 Boiler Start-up

WARNING

For your safety, when starting the boiler, keep your
head and face well away from the burner area to
prevent any risk of personal injury.

AVERTISSEMENT

Pour votre sécurité personnelle lorsque vous
mettez l’appareil en marche, tenez votre tête et
votre visage loin du brûleur pour éviter tout risque
de blessure.

WARNING

Vent pipes, and heater tops get hot! These surfaces
can cause serious burns. Do not touch these
surfaces while the heater is in operation.

AVERTISSEMENT

Les tuyaux d’aération et le dessus de l’appareil
deviennent chauds! Ils peuvent causer de graves
brûlures. Ne touchez pas à ces surfaces lorsque
l’appareil est en marche.

Caution

Do not use this boiler if any part has been under
water. Immediately call a qualified service
technician to inspect the heater and replace any
part of the control system and any gas control
which has been under water.

Attention

N’utilisez pas cet appareil s’il a été plongé dans
l’eau, même partiellement. Faites inspecter
l’appareil par un technicien qualifié et remplacez
toute partie du systéme de contrôle et toute
commande qui ont été plongés dans l’eau.

Содержание JVS

Страница 1: ...ed by a qualified installer service agency or gas supplier AVERTISSEMENT Assurez vous de bien suivres les instructions donn es dans cette notice pour r duire au minimum le risque d incendie ou d explo...

Страница 2: ...s Piping 12 5 2 Alternate Auto Bypass Operation 12 5 3 Flow Requirements 15 5 4 Chilled Water Systems 16 5 5 Oxygen Permeable Systems 16 5 6 Anti Freeze 16 SECTION 6 Electrical 6 1 General Information...

Страница 3: ...and Standards The JV Hydronic Boiler or Mini Therm II is design certified by CSA Canadian Standards Association as complying with the latest edition of the Standard for Gas Fired Low Pressure Steam a...

Страница 4: ...Diameter 225 7 Diameter 11 Electrical Supply 115 Volts AC 12 Modification of Boiler for High Altitude Mini Therm II Boilers are normally shipped from the factory in the low altitude sea level operati...

Страница 5: ...rovide at least six inches clearance between the automatic vent damper and combustible construction and be sure to allow access for servicing the damper 6 Install the temperature pressure gauge provid...

Страница 6: ...ater by at least 12 inches 305mm in all directions The masonry must be laid with ends unsealed and joints matched to provide free circulation of air from side to side through the masonry see Figure 4...

Страница 7: ...afe boiler operation AVERTISSEMENT N entrepposer aucun produit chimique produit nettoyant ou produit corrosif proximit des bouches d air de combustion ou dans la pi ce viter de placer des tuyaux de ve...

Страница 8: ...ing system This can create a health hazard by spilling flue products into the boiler room Use engineered venting tables acceptable to the authority having jurisdiction to size the venting pipe or line...

Страница 9: ...instrumentation of this boiler replaces an older boiler in a common vent system with other appliances or if you remove additional appliances from the common vent all the appliances must be checked fo...

Страница 10: ...the figures in Table 4 to size the gas inlet piping from the gas meter to the heater Check all local codes for compliance before installing the heater flame of a match or candle or smoke from a cigar...

Страница 11: ...ahead of the gas controls see Figure 5 Fit the trap with a threaded cap which can be removed for cleaning 5 Install a manual gas shutoff valve for service and safety Do not use a restrictive gas cock...

Страница 12: ...40 F see Figure 6 Contact the factory for more information SECTION 5 Water Connections 5 1 Water Piping Figure 6 shows typical plumbing installations Be sure to provide unions and isolation valves at...

Страница 13: ...ary Piping with Field Balancing for Fixed Low Return Temperatures JV Pump Isolation Valve Isolation Valve Balancing Valve Balancing Valve Pump From System To System Tempering Valve with System Loop an...

Страница 14: ...R Air Scoop JV Boiler Bypass Valve Ball Valve Zone Pump Purge System Optional Pump Location Feed Water Inlet Air Cushion Type Expansion Tank Optional Feed Water Inlet System Loop Expansion Tank Pump A...

Страница 15: ...is manual Figure 7 By pass Piping Balancing Valve or optional thermostatic union Laars P N 2400 030 Primary Secondary only To System From System In Return Out Supply Drip Leg Left Side View A full siz...

Страница 16: ...iquetez tous les fils avant de les d brancher Des erreurs de c blage peuvent entra ner un fonctionnement inad quat et dangereux 6 1 General Information Wiring connections must be made exactly as shown...

Страница 17: ...GR 24V TH W MV SPARK 1 2 3 4 5 6 7 8 9 REMOTE FLAME SENSOR HIGH ALTITUDE OPTIONAL Figure 9a Wiring Diagram Spark Ignition System JVS 50 75 Switch Safety Roll Out Blocked Vent Safety Switch Space Heat...

Страница 18: ...LAARS Heating Systems Page 18 Figure 9c Wiring Diagram Standing Pilot System JVT Figure 9d Schematic Standing Pilot System JVT...

Страница 19: ...WITH THE APPLIANCE MUST BE REPLACED IT MUST BE REPLACED WITH APPLIANCE WIRING MATERIAL SUITABLE FOR 105 DEGREES C OR ITS EQUIVALENT 1 2 3 4 5 6 THE BOILER WILL NOT OPERATE WITHOUT THE AUTOMATIC VENT...

Страница 20: ...primary secondary pumping Connect to W in lieu of A Boiler relay is used for boiler pump and connection to W will energize boiler pump when any zone is calling for heat Wiring with Taco Zone Valves W...

Страница 21: ...6 4 2 Heat Anticipator For single zone installations the wall thermostat heat anticipator should be set at 0 5 amperes For multi zone installations have a qualified electrical technician make the nece...

Страница 22: ...on tanks require visual inspection of liquid level If necessary inspect the liquid level in the expansion tank With the system full of water and under normal operating pressure to ensure proper water...

Страница 23: ...Read and follow all safety instructions first A more detailed set of lighting and shutdown instructions are listed on the label located on the boiler NOTE If your boiler is configured to operate on LP...

Страница 24: ...your building a 3 Immediately call your gas supplier from a neighbor s phone Follow the gas supplier s instructions a 4 If you cannot reach your gas supplier call the fire department All Models 4 Shu...

Страница 25: ...xide in flue gases which could result in severe injury or death AVERTISSEMENT Une installation ou un entretien inad quat peut causer la naus e ou l asphyxie en raison du monoxyde de carbone pr sent da...

Страница 26: ...the safety of the equipment depends on their proper functioning It is strongly recommended that the basic items listed below be inspected by a qualified service technician every year a Water temperat...

Страница 27: ...ated in the draft diverter opening on the rear of the boiler 7 Rollout Switch JVS and JVT boilers are equipped with a manual reset rollout switch designed to shut the boiler down in the event a flame...

Страница 28: ...oisy A Air in volute A Bleed air from volute Check pump alignment B Worn coupling or bearings B Replace worn parts 8 Boiler pounding A Too low water flow through boiler A Check temperature rise betwee...

Страница 29: ...wire Clean flame rod Check electrical connections between flame rod and module Check for cracked ceramic flame rod insulator Check that pilot flame covers flame rod and is steady and blue Adjust pilo...

Страница 30: ...hermocouple may be defective 11 There are two tests necessary to make sure the problem is not in the pilot thermocouple The first test can be performed by unscrewing the compression fitting on the gas...

Страница 31: ...section of piping which connects the boiler return and supply with the branch es Also known as a main or header Should be same size as boiler inlet outlet connections Vent Damper optional in Canada S...

Страница 32: ...2900 L0032900 L0032900 L0032900 L0032900 L0032900 L0032900 L0032900 L0032900 Gas Manifold L0052601 L0052601 L0052602 L0052602 L0052603 L0052603 L0052604 L0052604 L0052605 L0052605 L0052606 L0052606 El...

Страница 33: ...4 20034905 20034905 20034906 20034906 Access Panel HX L R 10535900 10535900 10535900 10535900 10535900 10535900 10535900 10535900 10535900 10535900 10535900 10535900 Base Control Box 20086800 20086800...

Страница 34: ...4 Hold 1 7 8 Hold Aquastat Bulb Cover Control Box Temperature Pressure Gauge Jacket One Piece Wraparound A B C A Inlet Pipe B 4 1 2 x3 4 Pipe C Outlet Pipe Gas Valve Flame Roll Out Safety Switch Burn...

Страница 35: ...Mini Therm II Hydronic Boiler Page 35...

Страница 36: ...x 800 559 1583 Customer Service Service Advisors 20 Industrial Way Rochester NH 03867 603 335 6300 Fax 603 335 3355 1869 Sismet Road Mississauga Ontario Canada L4W 1W8 905 238 0100 Fax 905 366 0130 ww...

Отзывы: