19
3.9.1 Installing AC Input Ground Cable
Step 1
Remove the rear cover from the DCPS, as shown in Figure 25.
Figure 25 – Removing the rear cover from the DCPS
Step 2
Remove the AC input protective cover, as shown in Figure 26.
Figure 26 – Removing the AC protective cover
Step 3
Route the AC input ground cable through an appropriate cable hole on the rear of the
subrack.
Step 4
Secure the AC input ground cable to the corresponding AC input ground terminal by using
M6X16 bolts, spring washers, and flat washers. Figure 27 shows an AC input ground terminal