SUPERSTRUCTURE OPERATION
Operating instructions • Semitrailer • 505369471-04 • 02/2019
97
KRONE trailers can be equipped with sev-
eral pairs of one of the following sliding
post types:
○
One-part fold-out posts
One-part fold-out posts", pg. 97)
○
Telescopic fold-out posts
Telescopic fold-out posts", pg. 98)
○
and locking double-deck posts", pg. 101)
Preparing to move the centre posts
► Open the curtain.
► Remove any tension chains between
the centre posts and the board walls.
Lateral load compartment limiter", pg. 94)
.
eral load compartment limiter", pg. 94)
ü
The centre posts are prepared for
shifting.
Top bearings of sliding posts
The sliding posts are mounted on rollers
that run in the continuous external beams
of the roof frame.
1
2
3
Fig. 6-61:
Bearings of sliding posts
1
External beam
2
Bogie truck with rollers
3
Sliding post
6.2.10.1 One-part fold-out posts
KRONE trailers with sliding curtain super-
structures are equipped with one-part fold-
out posts.
Depending on their design, one-part fold-
out posts have
○
several sets of lath sockets for plug-in
laths, and
○
one set of lath sockets above the floor,
each for four plug-in laths.
Posts without lath sockets are also pos-
sible.
1
2
3
Fig. 6-62:
One-part centre post
1
Flat lath sockets
2
Lath depot
3
Locking lever
Moving and locking one-part fold-out
posts
þ
The centre posts are prepared for slid-
ing
(see "6.2.10 Centre posts", pg. 96)
► Pull out the locking lever and com-