100
451253/A
System tests
Topics
Visual inspection of units, page 102
Signal transmission check - ringing, page 108
Final installation checks, page 109
Scope
After the installation has been performed and before the SBP 29 system is brought into
operation for the first time, a series of test procedures must be carried out to confirm a
correct installation.
Some of the tests can be carried out on individual units once that particular unit has
been installed. However, in the interests of safety and to avoid possible mistakes, it is
recommended to set aside a period of time at the end of the installation phase specifically
for the checks and tests. The entire set of tests can then be performed in sequence to
ensure the entire system is comprehensively checked.
Note
If the test engineer is not satisfied with the quality of any part of the installation, he/she
must contact the customer to have the work rectified and brought up to the required
quality standards.
Which specific tests that are to be conducted are normally specified in the contract. In
most cases, the following tests are performed
• Installation tests
– These tests are performed during the installation work. The general procedures are
given in this chapter. These tests take place before power is applied to the system.
• Setting To Work (STW)
SBP 29 Installation Manual
Содержание SBP 29
Страница 1: ...451253 A November 2019 Kongsberg Maritime AS SBP 29 Sub bottom profiler Installation Manual ...
Страница 57: ...451253 A 57 Cable plan overview Overview of the SBP 29 cable plan Cable layout and interconnections ...
Страница 111: ...451253 A 111 Figure 12 862 216859 Drawing files ...
Страница 112: ...112 451253 A Figure 13 307904 SBP 29 Installation Manual ...
Страница 113: ...451253 A 113 Figure 14 862 218001 Drawing files ...
Страница 114: ...114 451253 A Figure 15 871 219193 SBP 29 Installation Manual ...
Страница 115: ...451253 A 115 Figure 16 871 219201 Drawing files ...
Страница 116: ...116 451253 A Figure 17 388168 SBP 29 Installation Manual ...
Страница 117: ...451253 A 117 Figure 18 871 219187 Drawing files ...
Страница 118: ...118 451253 A Figure 19 821 219199 SBP 29 Installation Manual ...
Страница 119: ...451253 A 119 Figure 20 388235 Drawing files ...
Страница 120: ...120 451253 A Figure 21 871 219198 SBP 29 Installation Manual ...
Страница 121: ...451253 A 121 Figure 22 388148 Drawing files ...
Страница 122: ...122 451253 A Figure 23 315550 SBP 29 Installation Manual ...
Страница 123: ...451253 A 123 Figure 24 430751 Drawing files ...
Страница 124: ...124 451253 A Figure 25 871 212984 SBP 29 Installation Manual ...
Страница 125: ...451253 A 125 Figure 26 407070 Drawing files ...
Страница 126: ...126 451253 A Figure 27 448231_1A SBP 29 Installation Manual ...
Страница 127: ...451253 A 127 Figure 28 427512 Drawing files ...
Страница 128: ...128 451253 A Figure 29 435680 SBP 29 Installation Manual ...
Страница 129: ...451253 A 129 Figure 30 444783 Drawing files ...
Страница 151: ......
Страница 152: ... 2019 Kongsberg Maritime ...