TP-6514 9/09
29
Section 1 Installation
4. Connect the engine start leads from the automatic
transfer switch or remote start switch to terminals 3
and 4 on the terminal block. See Section 1.8.2.
5. The
terminal
block
kit
includes
120 VAC
receptacles for the battery charger and optional
carburetor heater.
Connect utility power to the
terminal block as shown. Connect to a circuit that is
supplied by the generator set if utility power is lost.
See Section 1.5 for more information about the
120 VAC power requirement.
Field Connections, TRES (3-phase) Models
See Figure 3 in the Introduction section of this manual
for the terminal block location.
See Figure 1-31 for
terminal block details.
Leads have been factory-
installed from the junction box to the terminal block for
easy field wiring. Make field connections to the terminal
block. Refer to the decal near the terminal block for
connections.
1. Remove the cable inlet cover. See Figure 1-30.
2. Drill holes for the cable fittings into the cable inlet
cover and reinstall the cover.
3. Remove the circuit breaker cover.
4. Feed the cables through the openings in the cover
and connect the cables. Refer to Figure 1-31 and
the decal near the terminal block. See Section
1.8.3, Grounding, and Section 2, Wiring Diagrams.
5. Connect the engine start leads from the automatic
transfer switch or remote start switch to terminals 3
and 4 on the terminal block. See Section 1.8.2.
6. Connect utility power (for the battery charger and
carburetor heater) to the terminal block as shown
on the label. Connect to a circuit that is supplied by
the generator set if utility power is lost. See Section
1.5 for more information about the utility power
requirement.
7. Verify that the cables are secure and there is no
stress on the connections.
8. Replace the circuit breaker cover.
1
GM66010
1. Terminal block and circuit breaker cover
2. Cable inlet cover
2
Figure 1-30
TRES (3-phase) Models
1. Engine start connection
2. Utility ground
3. Utility 230V power connection (see label)
4. Auxiliary contact (factory connection)
5. Load connections
6. Ground (earth)
6
GM66066
3
5
4
2
1
Note:
See the label near the terminal block for
connections.
N5 = Mains Neutral
M5 = Mains Live
Figure 1-31
Field Connection, TRES (3-phase)
Models
Содержание 12RES
Страница 4: ...TP 6514 9 09 4 Notes ...
Страница 18: ...TP 6514 9 09 18 Section 1 Installation Figure 1 6 Generator Set Clearances 17RES and 18RES ADV 7341 B Sheet 2 ...
Страница 20: ...TP 6514 9 09 20 Section 1 Installation Figure 1 8 Generator Set Clearances 18TRES 3 phase ADV 7713 Sheet 2 ...
Страница 44: ...TP 6514 9 09 44 Section 2 Wiring Diagrams Figure 2 2 Schematic Diagram Single Phase 8 5 12RES ADV 7325 D ...
Страница 46: ...TP 6514 9 09 46 Section 2 Wiring Diagrams Figure 2 4 Schematic Diagram Single Phase 17 18RES ADV 7353 F ...
Страница 48: ...TP 6514 9 09 48 Section 2 Wiring Diagrams Figure 2 6 Schematic Diagram Three Phase 12TRES ADV 7623 Sheet 4 ...
Страница 50: ...TP 6514 9 09 50 Section 2 Wiring Diagrams Figure 2 8 Schematic Diagram Three Phase 18TRES ADV 7637 Sheet 3 ...
Страница 52: ...TP 6514 9 09 52 Section 2 Wiring Diagrams Notes ...
Страница 55: ......