Vacuum pump system SCC 950
Setup and connection
Translation of original Operating Instructions, English, KNF 304771-304773 07/18
21
3.) Wall installation (Fig. 6, bottom)
Foot in top position
Wire support in top position and folded down
Fixing screw (Fig. 6/
9
) tightened
Hand terminal on charging station and fixed in place with
the transport holder (Fig. 6/
8
) (optional)
1. Hang the charging station on the wall (hanging points, see
arrows in Fig. 7).
2. Tighten the screws
Fig. 7: Charging station fixed to a wall
4.) Attachment to the vacuum pump system (Fig. 6, bot-
tom)
Foot in top position
Wire support in top position and folded down
Fixing screw (Fig. 6/
9
) tightened
1. Loosen the two Allen screws (Fig. 8/
1.
) so that the bracket can
be mounted.
2. Mount the enclosed bracket (Fig. 8/
2.
).
3. Tighten the two Allen screws again.
4. Hang the charging station on the four screws in the bracket
3.
, hanging points, see arrows in Fig. 7).
5. Tighten the four Allen screws.
6. Place the hand terminal on the charging station (Fig. 8/
4.
) and
fix in place with the transport holder (Fig. 6/
8
) (optional)
Fig. 8: Attaching the charging station to the SCC 950 vacuum pump
system
Requirements
Requirements