Installation
July 2018
4-6
06-237518-001
4-6
CYLINDER BANK INSTALLATION
Before the cylinder installation begins, it is strongly recommended that door(s) to the cylinder
storage room are secured in the OPEN position. Use signs and warning tape to restrict access
to the area. No other tasks should be performed while installing the cylinders.
4-6.1
Location
The cylinders and associated fixing equipment shall be placed and installed according to the
project specific cylinder bank assembly layout.
4-6.1.1
Typical Floor Load
Ensure the floor can support the total load of the cylinders. Use these table to calculate the
floor load of the cylinder bank.
Note:
When cylinders banks are installed on top of subfloors, additional supports under the
subfloor may be required.
Table 4-5. Approximate Weight per Meter of 80.0 Litre Cylinders
Number of
Rows
IG-100
IG-541
IG-55
IG-01
Weight (Kg)
Weight (Kg)
Weight (Kg)
Weight (Kg)
200 bar
300 bar
200 bar
300 bar
200 bar
300 bar
200 bar
300 bar
Single row
363
383
380
408
378
405
395
431
Double row
725
766
760
816
755
811
789
863
Triple row
1088
1149
1140
1225
1133
1216
1183
1294
Table 4-6. Approximate Weight per Meter of 140.0 Litre Cylinders
Number of Rows
IG-100
IG-541
IG-55
IG-01
Weight (Kg)
Weight (Kg)
Weight (Kg)
Weight (Kg)
Single Row
723
768
763
808
Double Row
1447
1535
1525
1616
Triple Row
2170
2303
2288
2424
Содержание 400 Series
Страница 2: ...Table i Revision History Revision Change Description AA Initial Release ...
Страница 16: ...July 2018 xiv 06 237518 001 THIS PAGE INTENTIONALLY LEFT BLANK ...
Страница 157: ...06 237518 001 A 1 July 2018 APPENDIX A SAFETY DATA SHEETS ...
Страница 188: ...July 2018 A 2 06 237518 001 THIS PAGE INTENTIONALLY LEFT BLANK ...
Страница 189: ......