6. Working environment requirement:
(1) Temperature : 0
℃
~ 45
℃
.
(2) Humidity : 40% ~ 75%.
7. When positioning the machine, do not operate the machine under these
environments:
(1) The location where oil
、
water
、
chip might splash.
(2) The location where there are strong electromagnetic devices or electro
welding machines nearby.
(3) The location where there are vibrational sources, such as punching
machine, press machine, shearing machine surrounded.
(4) The location where exposed under the sunlight.
(5) The location where the ground is inclining or slide.
3-3.
Installation instruction:
1. Put the machine on the planned foundation firstly.
2. Put the foundation bolts and foundation brackets beside the foundation holes
Temporarily.
3. Lift up the machine, and then put in the foundation bolts, and brackets to the
holes of leveling screws, then tight up the nuts to prevent the falling.
4. Lift down the machine on the ground, and then insert the foundation bolts into
the foundation holes.
5. Pour a little of the concrete into the foundation hole firstly, please notice that the
concrete should use the suitable proportion, and expanding coefficient in order
to prevent the shrink effect after adjusting.
6. After the foundation bolts are in the leveling screws, and then please pour the
concrete into the foundation holes and fill it. After that please level the machine.
7. After leveling, please screw up the leveling nuts of the leveling screws,
foundation bolts and hexogen nut.