Kemlan TEMPO 3 Скачать руководство пользователя страница 8

50

12mm 
Air gap

150

Run a bead of silicone down
the vertical seam of the outer 
casing to the flashing

Ceiling trim

7” Flue

TEMPO 3 VER 2 FREESTANDING

FLAT CEILING INSTALLATION

4.5” Flue

Flash roof to outer casing

(supplied by installer)

INSTALLATION INSTRUCTION

Pop rivet or
screw brackets to
the outside of the
outer casing

Short tube fits into flue
pipe. All flues should
be trimmed level

DETAIL A

DETAIL B

7” Decro

A

Stainless steel flue pipe.
All flue pipes must be
connected with pop rivets
supplied by installer

All casing flue pipes must
be connected with pop
rivets supplied by installer

Flue system to be installed
to suit AS/NZS 2918.2001

50

Vented cap

B

Support outer flue with
Brackets supplied

Bracing supplied by installer

NOTE:- When Decromesh/Heatshield is fitted, it must 
finish a minimum of 600mm below the ceiling or extend 
through the ceiling drop box into the outer flue casing

9” Flue

All

4.5” assembled flues must 

have the crimps pointing 
downwards 

crimped

plain

DETAIL C

DETAIL D

All

7”-9” assembled flues must 

have the crimps pointing upwards 

plain

crimped

C

D

NOTE:- When Decromesh/Heatshield is fitted, it must 
finish a minimum of 600mm below the ceiling or extend 
through the ceiling drop box into the outer flue casing

21/08/2020

Ver.7

8

Содержание TEMPO 3

Страница 1: ...IT ON COMPLETION 10 YEAR FIREBOX WARRANTY The firebox is covered by a 10 year warranty Other parts are covered by a one year limited warranty Head Office 13 French Avenue Brendale Queensland 4500 Telephone PH 07 3490 5500 Facsimile FAX 07 3490 5520 Website www jetmaster com au Business hours Monday to Thursday 7 30am 4 00pm Friday 7 30am 2 00pm Email sales jetmaster com au ...

Страница 2: ...DIMENSIONS TEMPO 3 VER 2 FREESTANDING UNIT A A B C D E F G H MEASUREMENTS 602 420 678 632 343 509 646 246 D B C E F 21 08 2020 Ver 7 2 G H ...

Страница 3: ...DIMENSIONS TEMPO 3 VER 2 FREESTANDING UNIT A D B C E F 21 08 2020 Ver 7 3 A B C D E F G MEASUREMENTS 602 420 678 632 296 532 580 G ...

Страница 4: ...21 08 2020 Ver 7 4 A D C B A B C D MEASUREMENTS 391 817 420 602 DIMENSIONS TEMPO 3 VER 2 FREESTANDING UNIT WITH MERIDIAN TABLE ...

Страница 5: ...IMPORTANT BAFFLE PLATE MUST BE PULLED FORWARD TOWARDS THE FRONT OF THE BOX UPON INSTALLATION AND BEFORE OPERATION CHAMFERED BAFFLE PLATE CORNERS TO BE POSITIONED ON THE FRONT LEFT AND FRONT RIGHT CORNERS ONLY MAKE SURER THERE ARE GAPS EITHER SIDE OF THE BAFFLE PLATES ...

Страница 6: ...IDES SLIDE THE BAFFLE PLATE ON A SLIGHT ANGLE TOWARDS THE BACK OF THE UNIT MAKE SURE TO PLACE ABOVE THE AIR TUBE PUSH BACK AS FAR AS POSSIBLE ALSO CHAMFERED BAFFLE PLATE CORNERS MUST BE ON THE FRONT LEFT AND FRONT RIGHT CORNER OF THE APPLIANCE PUSH THE BAFFLE PLATE SIDE WAYS UNTIL IT IS AGAINST THE SIDE WALL THEN PULL IT FORWARD AND LET IT REST ON THE FRONT TAB THIS WILL ALLOW FOR MORE ROOM FOR TH...

Страница 7: ...opening and 250mm to the sides The unit must be positioned centrally to the hearth When installed with an additional 900mm high x 180 deg stainless steel rear flue shield fitted between the decromesh casing and the active flue the rear wall clearance can be reduced to 150mm from a combustible wall Clearances to combustibles as per AS NZS 2918 755 300 800 125 125 755 300 800 ...

Страница 8: ...ue pipes must be connected with pop rivets supplied by installer Flue system to be installed to suit AS NZS 2918 2001 50 Vented cap B Support outer flue with Brackets supplied Bracing supplied by installer NOTE When Decromesh Heatshield is fitted it must finish a minimum of 600mm below the ceiling or extend through the ceiling drop box into the outer flue casing 9 Flue All 4 5 assembled flues must...

Страница 9: ...st be connected with pop rivets supplied by installer Flue system to be installed to suit AS NZS 2918 2001 50 Vented cap B Bracing supplied by installer All casing flue pipes must be connected with pop rivets supplied by installer 12MM AIR GAP 7 Decro 7 Flue 4 5 Flue NOTE When Decromesh Heatshield is fitted it must finish a minimum of 600mm below the ceiling or extend through the ceiling drop box ...

Страница 10: ...20 Ver 7 3000 OR LESS INCREASE FROM 1000 MIN UNTIL CLEAR WITHIN 3000 OF TOP OF FLUE 3000 ANY NEARBY STRUCTURE 6000 MORE THAN 3000 600 MIN 3000 1000 MIN IF CLEAR WITHIN 3000 OF TOP OF FLUE INCREASE AS NECESSARY UNTIL NOTHING WITHIN 6000 OF THE FLUE TOP 600 MIN 3000 OR LESS MORE THAN 3000 DIMENSIONS IN MILLIMETRES ...

Страница 11: ...21 08 2020 Ver 7 11 ...

Страница 12: ...mately 10 to 15 minutes until the new pieces are burning well then it may be returned to its desired setting 6 To set the fire for overnight burn two thirds fill the firebox with hardwood and fully open the air inlet Once the fire is burning well the air inlet control should be shut down approximately three quarters of its travel Setting the air inlet control may be varied to suit your particular ...

Страница 13: ... with higher heat production than wet or green wood The difference between the amount of heat produced by dry wood and green wood is so great that a dry softwood of good grade will produce more heat than green hardwood Green white ash for instance is not as good a fuel as dry tamarack The reason for the superiority of dry wood is easy to understand Heat cannot be produced until moisture has been d...

Страница 14: ... of inspection for damaged heater 5 CLAIMS 5 1 I Kemlan will provide a full replacement of the heater in the first five years after installation ii Replacement in the subsequent five years i e sixth to tenth year after installation will be on the following basis Owner will pay fifty percent of the current retail price if the claim is made in the sixth year tenth year after purchase 5 2 Replacement...

Отзывы: