Start-up
© KEB, 2008-02
COMBIVERT R6-S
Page 4.2 - 3
4
10
4.2 Start-up
After all preparatory measures have been carried out and checked the KEB COMBIVERT can be switched
on.
All control releases
ST (X2A.12) must be deactivated when switching on the first
time, since the COMBIVERT
R6-S is not custom-specific parameterized.
The following descriptions suppose that the COMBIVERT is on the password level "application mode" (ud.01
= application mode). The selection of the password level is described in the manual chapter 2.2. The start-up
should be executed with COMBIVIS in order to have a short start-up time.
Operating lists are available on the KEB homepage (www.keb.de). This lists contain the necessary parameters
for start-up.
Attention: The start-up instruction manual can only give a short overview of the parameter adjustments which
are mandatory necessary to start-up the COMBIVERT.
Thus it represents a check list and not a complete parameter description.
The appropriate chapters of the application manual must be read carefully for exact information about the pa-
rameters, additionally points to consider and application-specific adjustments!
The units are not short-circuit proof without corresponding dimensioned fuses!
Exceeding of the max. rechargeable DC link capacity can lead to a defect!
A load removal in the DC link circle may be done only after the message „ready“!
The wiring must be checked before start-up, particularly the wiring of the control release of the connected inver-
ters (see page 1.3-8). No parameterizations are needed for power supply operation. A vew parameter settings
are necessary only for regenerative operation.
4.2.1 R6-S operation power supply and regenerative unit
No parameter settings are necessary in the operating mode as power supply and regenerative unit when
using a R6-S unit and KEB commutation choke or harmonic filter based on default settings and Pn
.19 (CP.33).
Pn.19 Operating mode
The parameter defines whether the respective R6 unit is operated as master or slave, with commutation choke
or harmonic filter
.
With parameterization of Pn.19 (CP.33), cS.00 and cS.01 (data commutation choke) as well as cS.04 (control
angle) are preset for the actual R6 unit (reference to the power unit code) and the appropriate choke or har-
monic filter.
Choke rating data
cS.00 Choke/rated voltage, cS.01 Data commutation choke
Setting in accordance with the data sheet of the choke.
Parameters are preset with Pn.19 (CP.33). Only relevant for special chokes!
Содержание combivert R6-S
Страница 1: ...APPLICATION MANUAL Mat No Rev 00R6SEA K130 1 A GB KEB COMBIVERT R6 S Version 1 3 ...
Страница 2: ...Page 1 1 2 COMBIVERT R6 S KEB 2008 02 Introduction ...
Страница 4: ...Page 1 1 4 COMBIVERT R6 S KEB 2008 02 Introduction ...
Страница 14: ...Page 1 2 6 COMBIVERT R6 S KEB 2008 02 Product overview ...
Страница 28: ...Page 2 1 6 COMBIVERT R6 S KEB 2008 02 Fundamentals ...
Страница 34: ...Page 2 2 6 COMBIVERT R6 S KEB 2008 02 Password structure ...
Страница 40: ...Page 3 1 2 COMBIVERT R6 S KEB 2008 02 Parameter overview 3 1 1 Parameter list F5 A E and H 3 1 3 ...
Страница 116: ...Page 3 8 2 COMBIVERT R6 S KEB 2008 02 Special functions 3 8 1 Program timer counter 3 8 3 ...
Страница 130: ...Page 3 9 10 COMBIVERT R6 S KEB 2008 02 Define CP Parameters ...
Страница 140: ...Page4 2 2 COMBIVERT R6 S KEB 2008 02 Start up ...
Страница 144: ...Page4 2 6 COMBIVERT R6 S KEB 2008 02 Start up ...
Страница 146: ...Page 5 1 2 COMBIVERT R6 S KEB 2008 02 Error assistance 5 1 1 General 5 1 3 5 1 2 Error messages and their causes 5 1 3 ...
Страница 150: ...Page 5 1 6 COMBIVERT R6 S KEB 2008 02 Error assistance ...
Страница 158: ...Page 6 1 8 COMBIVERT R6 S KEB 2008 02 Project design ...
Страница 160: ...Seite 7 1 2 COMBIVERT R6 S KEB 2008 02 Annex 7 1 1 Keyword index 7 1 3 ...
Страница 166: ......
Страница 167: ......