14
4 - RECEPTION
4.1 -
DELIVERY CONTROL
Before accepting the delivery, you have to check:
•
that the unit hasn’t been damaged during transport.
•
Check that the materials delivered correspond with that
indicated on the transport document comparing the data
with the identification label ‘
A
’ positioned on the
packaging.
In case of damage or anomaly:
•
Write down on the transport document the damage you
found and quote this sentence: "Conditional acceptance
clear evidence of deficiencies/damages during transport".
•
Contact supplier and the carrier by fax and registered mail
with advice of receipt.
Use protection (A) to avoid the unit damaging
Stair climbing trolley.
4.2 -
HANDLING
The following examples are indications the choice of the
means and of the handling modes will depend on factors.
Verify the lifting equipment's load-bearing capacity: the
shipped unit weighs
Unit
Shipping weight
190
kg
126
300
kg
149
Identify critical points during handling (disconnected routes,
flights, steps, doors).
Maximum inclination
When transporting the unit, do not carry it by holding on to the
top part of the circuit.
This unit is heavy, it need to be carried by two or more persons,
otherwise might cause injury and damage.
In order to avoid scratch or deformation of the unit surface,
apply guard boards to the contacting surface.
No contact of fingers and other things with the vanes.
While moving it, do not tip the unit to an angle less than 45°
and keep it in a vertical position during installation.
If the unit has been tipped during transport, wait at least 2
hours before starting it up