FOLD DOWN GUARDRAIL
INSTALLATION PROCEDURE
Step 1: Post and bracket installation
– Insert M10 x 90mm SS Bolt, 2 washers and 2
nyloc nuts.
– When doing up the nut, the nut must not be
tight on the bracket.
– Allow approx 1mm gap to allow post to move.
Step 2: Set out base channels
– Base channels must be set out at no more
than 2000mm apart.
– Drill out base channel (4 x 6mm holes).
– Fix base channels to roof deck with 4 x 5mm
bulb-tite rivets.
Step 3: Assemble the post/bracket to the base
channel
– Fix the bracket to the channel using 6 x 20mm
tek screws.
– Ensure the post is vertical before fixing off
completely.
www.sayfa.com.au
June 2015
CALL 1300 301 755
Page 3
NOTE!
1 Fold Down section comprises of 3 posts and
4000mm of Guardrail.
Assemble the post to the
Bracket.
Insert M10 x 90mm SS Bolt,
2 washers and 2 nyloc nuts.
When doing up the nut, the
nut must not be tight on the
bracket. allow approx 1mm
gap to allow post to move.
1
Post/Bracket Assembly
Nyloc Nut
Washer
Washer
M10 x 90
Bolt
INSTALLATION GUIDE
SENTRY
FOLD DOWN
GUARDRAIL SYSTEM
FOLD DOWN GUARD RAIL SYSTEM
It is very important to ensure these channels are in line with
each other and that the roof deck is in line. (if not, this will cause
problems with the folding mechanism)
www.sayfa.com.au
June 2015
CALL 1300 301 755
Page 5
Assemble the post/bracket to
the Base Channel.
Fix the bracket to the channel
using 6 x 20mm Tek Screws.
Ensure the post is vertical
before fixing off completely.
3
INSTALLATION GUIDE
SENTRY
FOLD DOWN
GUARDRAIL SYSTEM
FOLD DOWN GUARD RAIL SYSTEM
www.sayfa.com.au
June 2015
CALL 1300 301 755
Page 5
Assemble the post/bracket to
the Base Channel.
Fix the bracket to the channel
using 6 x 20mm Tek Screws.
Ensure the post is vertical
before fixing off completely.
3
INSTALLATION GUIDE
SENTRY
FOLD DOWN
GUARDRAIL SYSTEM
FOLD DOWN GUARD RAIL SYSTEM
www.sayfa.com.au
June 2015
CALL 1300 301 755
Page 4
Set out base channels.
Base channels must be set out
at no more than 2000mm
apart. Drill out base channel
(4 x 6mm holes). Fix base
channels to roof deck with 4
x 5mm Bulb-tite rivets.
IMPORTANT!
It is very important to ensure
these channels are in line with
each other and that the roof
deck is in line. (if not, this will
cause problems with the
folding mechanism)
2
5mm Bulb-tite rivet
Base Channel
Nitrile foam seal
Roof Deck
2m M
ax
Note:-
1 Fold Down section comprises of 3 posts and
4000mm of Guardrail.
Guardrail Installation
INSTALLATION GUIDE
SENTRY
FOLD DOWN
GUARDRAIL SYSTEM
FOLD DOWN GUARD RAIL SYSTEM
www.sayfa.com.au
June 2015
CALL 1300 301 755
Page 4
Set out base channels.
Base channels must be set out
at no more than 2000mm
apart. Drill out base channel
(4 x 6mm holes). Fix base
channels to roof deck with 4
x 5mm Bulb-tite rivets.
IMPORTANT!
It is very important to ensure
these channels are in line with
each other and that the roof
deck is in line. (if not, this will
cause problems with the
folding mechanism)
2
5mm Bulb-tite rivet
Base Channel
Nitrile foam seal
Roof Deck
2m M
ax
Note:-
1 Fold Down section comprises of 3 posts and
4000mm of Guardrail.
Guardrail Installation
INSTALLATION GUIDE
SENTRY
FOLD DOWN
GUARDRAIL SYSTEM
FOLD DOWN GUARD RAIL SYSTEM
30
Kattsafe / Guardrail / Installation manual
Copyright, trademarks and product codes are property of Kattsafe.
Patents and design registrations may apply to these products.
Содержание GUARDRAIL
Страница 1: ...INSTALLATIONMANUAL GUARDRAIL...