12
C. DRYER ENCLOSURE REQUIREMENTS
Bulkheads and partitions
must be
made of noncombustible materials and
must be
located a minimum of
12-inches (30.48 cm), 18-inches (45.72 cm) or more is recommended for ease of installation, maintenance, and
service above the dryer outer top, except along the front of the dryer which may be partially closed in if desired.
The clearance between the bulkhead header and the dryer
must be
a minimum of 4-inches (10.16 cm) and must
not extend more than 4-inches (10.16 cm) to the rear of the front. The bulkhead facing
must not be
closed in
ALL
the way to the top of the dryer. A 1-inch (2.54 cm) clearance is required.
NOTE:
Allowances
must be
made for opening the control door.
Dryers may be positioned sidewall to sidewall. However, a 1/16” (1.5875 mm) minimum allowance
must be
made for the opening and closing of the control door and the lint door. It is suggested that the dryer be positioned
about 2 feet (0.61 meters) away from the nearest obstruction for ease of installation, maintenance, and service
(to be measured from the back guard). Refer to the
illustration above
for details.
NOTE:
Air considerations are important for proper and efficient operation.
IMPORTANT:
Even though a minimum of only 12-inches (30.48 cm) is required behind the dryer,
18-inches (45.72 cm) or more is suggested (especially when vertical venting is used).
The additional clearance is advantageous for ease of installation and service.
IMPORTANT:
When fire sprinkler systems are located above the dryers, a minimum of 18-inches
(45.72 cm) above the dryer console (module) is required. Dryers may be positioned
sidewall to sidewall, however, a 1/16” (1.5875 mm) minimum allowance is required
between dryers (or wall) for ease of installation and maintenance. Allowances
must
be
made for the opening and closing of the control door and the lint door.
Содержание D-78
Страница 58: ...ADC113373 1 04 01 02 25 2 12 12 02 25 ...