P/N 960-100929R_Rev. 7 {EDP #148849}
© 2017, JAPAN CASH MACHINE CO., LTD.
6 - 1 1
Calibration and Testing
iVIZION® SeriesNext-Generation Banknote Acceptor Unit
Section 6
Performance Tests
This portion explains the iVIZION Performance
Test Procedures. The following two (2) methods
exist to perform this Performance Test Procedure.
•
Performance Test using a PC
•
Performance Test using the External DIP Switches.
Choose one (1) of the two (2) above Performance
Test Procedures by selecting the one related to the
particular circumstance desired.
:
Performance Test Items using a PC
Table 6-2 lists the available Performance Test Items
and their purpose using a PC for testing.
PC Performance Test Preparation
Perform following steps to begin the Performance
Test Preparation Procedure:
1. Turn the iVIZION Unit’s Power Switch
OFF
.
2. Remove the Transport Unit from the Frame.
3. Set 8-Position DIP Switch #8 to
ON
.
4. Place the Transport Unit into the Frame.
5. Turn the iVIZION Unit’s Power Switch
ON
.
The Status LED will light a steady
Blue
Color.
6. Launch the “
JCM Tool Suite Standard Edition
”
Application. The Screen shown in Figure 6-52
will appear when the application becomes active.
7. Click on, and hold-down the “Service Mode”
selection
Pull-Down Menu
a
) and
Slide-down select “
Performance Test
” from the
Pull-Down Menu Selections (Figure 6-52
b
).
8. Activate
the
“
iVIZION Test Item VerX.XX
” Appli-
cation and the Screen shown in Figure 6-53 will
automatically appear.
Table 6-2
PC Performance Test Items
No.
Test Item
Test Purpose
Status LED
Stand
-by
Operating
1
Motor
Normal
Rotation
Testing the Transport
Motor rotation in a
Banknote intake
direction
Blue
Lit
Yellow
Flashes
2
Motor
Reverse
Rotation
Testing the Transport
Motor rotation in a
Banknote reject
direction
3
Stacker
Motor
Testing the Stacker
Motor’s movement
4
Cycle
Movement
Testing sequential
movement from
Banknote trans-
portation to stacking
at regular intervals
without Banknotes
5
Status LED
Indication
Testing the Status
LED Indications
Red
Green
Blue
6
Sensor ON/
OFF
Testing each
Sensor’s
Performance
Blue
Lit
Blue
Lit
7
DIP Switch
ON/OFF
Testing the 8-Position
DIP Switches
Performance
8
Banknote
Acceptance
Testing
Transportation,
Validation, Stacking
and Reject
Performance, and the
Vend Signal Output
Extinguished
(Out)
9
ICB Setting
(Reading
Ticket)
Setting the ICB
Enable, Disable and
Machine No.
Functions.
NOTE: Refer to Figure 6-1 and Figure 6-2
for the necessary Tools and Harness
Connections and USB Cable Type
Requirements respectively.
Figure 6-51
DIP Switch #8 Set ON
JCM Tool Suite Standard Edition
Figure 6-52
JCM Tool Suite Standard Edition
Screen
a
b
iVIZION Test Item VerX.XX Screen
Figure 6-53
iVIZION Test Item VerX.XX Screen
a
b
c
d
f
i
g
h
e