Do a thorough clean up of the whole area where the old manual lift
system was installed. Generally, there is accumulated dirt and swarf from
modifications / original build.
If the Camper Trailer is an older model check for rot in the floor. If
required, during the JackaJay installation use metal screws to drill into
steel chassis or backing plate.
If deemed necessary, use a variety of screws / bolts with washers and nuts
to ensure secure attachment of corner elbows and motor assembly.
If the floor timbers are substantially damaged you MUST repair the floor
to ensure there is an adequate timber / metal to secure the JackaJay lift
mechanism.
Ensure that all holes in the floor have been sealed up with silicone before
starting you installaiton. This will limit any dust and moisture ingress into the
camper
STOP POINT 7
Ensure that all manual winch system components
have been removed.
The camper floor has been cleaned and is ready for
JackaJay installation.
Tick here