6.1.2 Commissioning after shutdown
NOTICE!
Damage to the pump due to unprofessional commissioning!
–
After long-term storage, the pump should be commissioned by
ITT Bornemann GmbH.
6.1.3 Removing preservative
Only necessary for preserved pumps.
Chapter 4.4 ‘Removing preservative’ on page 24
6.1.4 Lubricating bearings/gears
Pumps with drive-side greased roller bearings are ready for use
when delivered.
Chapter 7.3.2 ‘Lubrication’ on page 64
).
6.1.5 Preparing auxiliary operating systems (if present)
WARNING!
Risk of injury due to the use of third-party systems!
–
Use only ITT Bornemann GmbH approved auxiliary systems.
1.
Ensure that the barrier fluid is compatible with the pumped medium.
2.
Determine the appropriate sealing system (
Pump data sheet).
3.
Install sealing system (
manufacturer's documentation, pump system
additional instructions).
4.
Ensure that the parameters have been met for the installed sealing system
(
pump data sheet, manufacturer's documentation).
Sealing system
Operation
Type SLH-4G, SLHS-4G
48
01/2016 JPB Rev. 5