
25
ä Attention
!
Increasing the maximum speed causes more noise and higher
energy consumption.
ä Attention
!
Before the wireless control switch can be logged on, the
ventilation unit must have been de-energized for 15 seconds!
ä Attention
!
If the power fails during the commissioning phase, wait at
least 2 minutes after the power has been restored! All
ventilation units in the immediate vicinity will also be in log-on
mode for the first 2 minutes!
Note
Each wireless control must be logged in separately. You can
register and commission up to 20 wireless controls.
5. Commissioning
5.1. Preparation
Prior to commissioning
●
The ventilation unit and accessories must be mounted.
●
The ductwork must be mounted.
●
The condensation drain must be mounted and the siphon
filled so that a water trap is present.
●
External and internal doors and windows must be closed.
●
There must be sufficient flow-through space under the inner
doors.
●
The adjustable valves must be fully open in
all
rooms.
Note
If you are unable to complete the wireless control log-in within 2
minutes, you can return the ventilation unit to the log-in mode by
disconnecting it from the power supply and restarting it after 15
seconds. Operations that have already been logged on will
remain logged on to the ventilation unit. During the log-in
procedure, the status LED flashes green.
Note
If a VKK coupler or a heat pump is fitted, you will need to
adjust the dipswitch settings. See Dipswitch settings on page
22 .
Содержание HRU ECO 350
Страница 1: ...Itho Daalderop HRU ECO 350 Installation manual...
Страница 2: ...Original document...
Страница 10: ...10 ithodaalderup 1 M N 480 125 00 ij 306 424 2 6 Dimension drawings...
Страница 39: ...39 8 Service parts 1 4 2 10 3 13 9 5 8 67 2012 1615 1811 14 17 19 Exploded view...
Страница 43: ...43...