BUILDING SPECIFICATIONS
2
•
Granulometry
-
Fractions going through the 0.08 sieve will be smaller than
half the fractions sieved with the 0.40 sieve. Measured by
weight.
-
Maximum aggregate size will be smaller than half the
compacted layer.
-
The fraction retained by Sieve 5 should at least have 50%
(weight) elements with two or more fracture surfaces.
-
Abrasion measured by Los Angeles test should be lower
than A 30.
-
The material must be non-plastic and the sand-content
equivalent must be over A 35.
-
CBR > 80 for 100% compaction, Modified Proctor Test
•
Compacted density
-
Over 100% of maximum density. Modified Proctor Test
density, even in singular project areas (edges, meeting
points, elements).
2.4. Reinforced concrete slab
•
Thickness
-
See civil works ground plan.
•
Reinforcement
-
Electro-welded mesh AEH 500 (fyk=5100 Kp/cm2)
•
Slopes
-
See civil works ground plan.
•
Contraction joints
-
every 5.0 m
-
width 4 mm
-
depth 40 mm
•
Expansion joints
-
every 25.0 m
-
width 20 mm
-
filled and sealed
•
Finishing process
-
Spreading and compacting with concrete screeder.
-
Surface smoothing by screeder.
-
Mechanical floating once concrete is resistant enough
(helicopter, fixed flat propeller).
-
Repeat previous operations as many times as necessary
until the desired finish is obtained. In our case, surface
finish must be non-slip.
-
Curing by wax-based curing liquid (Bettocure-C).