(2) Lift the inverter to suspend it on the installation bracket through 

M8 hex socket cap screws;   

(3) Finally, fix the inverter with the bracket. For firm installation, the 

operators cannot release the device until the inverter is installed on 

the bracket firmly. 

(4)Fasten the screws. 

 

Figure 4 Installation of inverter 

Electrical installation

 

 

Figure 5 Electrical wiring of the inverter 

 

OR   

 

Figure 6 Connection of the AC side and the inverter 

Below are the electrical wiring steps of the three-phase inverter:   

(1) Before connecting the three-phase AC grid cable to the inverter, 

take lightning and short circuit protection measures in accordance 

with the local electrical safety codes;   

(2) As shown in Figure 6, connect and fasten

L1

L2

L3

N (optional) 

and PE conductors of the three-phase common grid to AC terminal, 

and then connect the terminal to the AC port of the inverter;   

(3) Fix and connect the DC output  cables of PV board with the 

matched DC connectors, and then connect the connectors to the DC 

port of the inverter. 

Operation

 

5.1 Inspection before operation 

Check as follows before operation: 

(1) Detect the voltage of the components is in the allowable input 

voltage range of the inverter; 

(2) Detect the voltage of the AC port at AC side is normal; 

(3) Check the inverter is in good grounding; 

(4) Ensure all switches are “off”; 

(5)  Ensure all electrical safety  precautions are clearly-identified on 

the installation site. 

(6) Confirm the handheld keypad or communication module is in 

correct connection. 

5.2 Grid-tied operation 

Please start the inverter as follows:   

(1) Switch on the integrated DC switch; 

(2) Use the handheld keypad or communication module to set the 

time, date and area of the inverter;   

(3) Switch on the breakers at the AC side;   

(4) Observe the LED indicators and information displayed on the 

LCD 

screen.   

Run

  Green indicator blinks, others off: the inverter is power 

on and in self-inspection;

 

Run

  Green indicator on, others off: the inverter is in  power 

generation after self-inspection----successful commissioning.

 

“Warn”  or  “Fault”  indicators are on or blinking: the inverter is 

power on, but fault occurs.

 

5.3

 

Accessories and wiring   

The accessories are the handheld terminal, WiFi, ENET and GPRS. 

         

RS485

3

2

1

4

3

2

1

4

-M

RS485 -S

 

Connect the 485 port of accessories to the RS485-M(4-10kW) or 

RS485(12-40kW) port of the inverter; for the ACF inverter, 

RS485-M(4-10kW) or RS485(12-40kW) is to the upper PC and 

RS485-S(4-10kW) or EXT(12-40kW) is to the ammeter.   

5.4 Regular maintenance 

Stop the inverter as follows it needs maintenance, inspection and 

troubleshooting: 

(1) Switch off the breakers at the AC side;   

(2) Switch off the integrated DC switch; 

(3) Contact with customer service staff or local dealers. 