INTILION scalebloc 0.5C
77
6
Commissioning
The initial commissioning (trial run) of the battery storage system is performed by
INTILION GmbH or by personnel trained by INTILION GmbH under the supervision of the
system manager,
The system manager must have completed an INTILION scalebloc product training
session and briefing.
Following initial commissioning, the “System management” document must be signed in
duplicate. One copy is kept by INTILION GmbH and the second copy is stored in the
battery storage system.
For re-commissionings, contact INTILION GmbH
(see Section “1.5 Service/customer
WARNING
Risk of injury due to lack of space!
When commissioning the battery storage system, there is a risk of injury
such as scratches, puncture wounds or fractures as a result of an
excessively close arrangement of the necessary work equipment and/or
components.
•
Cordon off the danger zone.
•
Keep unauthorised persons away from the area.
•
Appoint a responsible person.
Make sure that you are sufficiently familiar with
–
The operating and control elements of the battery storage system
–
The equipment of the battery storage system
–
The way in which the battery storage system works
–
The immediate vicinity of the battery storage system
–
The safety devices in the battery storage system
–
The procedure to follow in an emergency
Содержание scalebloc 0.5C
Страница 33: ...2 Safety 2 10 Obligations of the system manager INTILION scalebloc 0 5C 31 ...
Страница 34: ......
Страница 46: ...4 Transport and storage 3 3 Technical specifications 44 INTILION GmbH ...
Страница 77: ...5 Installation 5 12 Establishing the mains connection INTILION scalebloc 0 5C 75 ...
Страница 78: ......
Страница 98: ...6 Commissioning 6 8 Contacting the Hoppecke Service team 96 INTILION GmbH ...
Страница 100: ......
Страница 102: ...8 Fault 100 INTILION GmbH ...