Application

 

The solar controller is integrated into domestic hot  water  systems in boilers 

(water heaters), combined with solar panels (fireplaces) and electric heaters. 

It  is  designed  to  monitor  the  differential  temperature  and  to  control  the 

operation  of  a  circulation  pump  mounted  in  the  water  circuit  between  the  panels 
(fireplace,  boiler)  and  the  boiler  coil.  This  regulates  the  heat  exchange  between 
them, helping to make the system more efficient. 

 

2. 

How it works

 

The controller has two temperature sensors installed in the  water heater and 

the solar panels. The operation of the controller is determined depending on the set 
parameters and the measured temperature. The following parameters are monitored 
during operation:  

2.1

  delta  T  (∆Т)

  –  Set  difference  between  panel  and  boiler  temperatures 

(differential  difference).  It  can  be  set  between  2  and  20  °C. 

Default  setting  is  10 

°C; 

2.2

 Tb

set

 – Set temperature in the boiler to which it can normally be heated 

by  solar  panels  (fireplace,  boiler).  It  is  set  in  the  range  from10  to  80  °C. 

Default 

setting is 60 °C

2.3

 Тb

max

 – Critical, maximum allowable temperature in the boiler. It is set 

between 80 and 100 °C. 

Default setting is 95 °C;

 

2.4

 Тp

min

 – Minimum temperature of solar panels. It is set in the range from 

20 to 50 °C. 

Default setting is 40 °C

;

 

2.5

 Тp

max

 

– Maximum permissible temperature of solar panels (fireplace). It 

is set between 80 and 110 °C. 

Default setting 105 °C

2.6

 Тp

def

 

– Defrosting temperature of solar panels. It is set in the range -20 to 

10 °C. Default setting without defrost - 

OFF

;

 

2.7

 Тb

min

 – 

Minimum temperature in the boiler below which the defrosting 

of the panel is stopped. Cannot be set. 

Default setting is 20 °C

;

 

2.8 

t

cool

  –  Time  to  delay  the  boiler  cooling  function  to  the  set  Tbset 

temperature. The controller will wait for the time specified in this setting to expire 
and if the condition is met Tp<Tb-2 °C, will turn the pump on until it reaches Tbset. 

Default setting is 4 hours. 

 

If  necessary,  a  correction  can  be  made  in  the  readings  of  the  measured 

temperatures: 

     

Tbc

 – 

Correction of the reading from the boiler temperature sensor;

 

           

Tpc

 

– Correction of the reading from panel sensor; 

The setting is in the range -10 to + 10 °C. The default is 0 °C. 

Deviations in the readings of the temperature values can be the result of cables that 
are too long or from poorly positioned sensors. 

 

Содержание DT-3.1

Страница 1: ...CTRONICS ON YOUR SIDE PROGRAMMABLE CONTROLLER FOR SOLAR SYSTEMS DT 3 1 USER S GUIDE INTIEL LTD 10 str Major Kolontaevski e mail office intiel gmail com 8200 Pomorie e mail office intiel com BULGARIA w...

Страница 2: ...2...

Страница 3: ...ted place away from heat sources and flammable gases or liquids Make sure that the mains voltage matches the voltage on the rating plate of the unit Use power consumers that match the power output of...

Страница 4: ...ax Critical maximum allowable temperature in the boiler It is set between 80 and 100 C Default setting is 95 C 2 4 pmin Minimum temperature of solar panels It is set in the range from 20 to 50 C Defau...

Страница 5: ...d the pump is forced to start even though it was switched off due to the temperature drop below pmin If in the previous mode the temperature of the boiler becomes lower than bmin the pump is switched...

Страница 6: ...cator of the temperature of the solar panels as well as a part of the menu showing the parameter to be adjusted 2 Boiler temperature indicator as well as part of the menu showing the value of the para...

Страница 7: ...automatically exits from the menu If this happens while changing a value the value is flashing then the change will not be stored in memory Lock menu access The menu can be locked to prevent unintenti...

Страница 8: ...the solar panels Terminals 10 11 are input for the sensor from the boiler A Pt1000 sensor is connected to them Terminals 1 2 and 3 are supplied with neutral phase and protective earth respectively fro...

Страница 9: ...lectric heaters RT working thermostat of the boiler BT blocking thermostat of the boiler Panel sensor Boiler Circulation pump Boiler sensor Solar panel L1 N PE L N PE Differential thermostat B R Elect...

Страница 10: ...c heaters RT working thermostat of the boiler BT blocking thermostat of the boiler Sensor Fireplace Heating N PE L2 L1 Boiler sensor Boiler Open Close Differential thermostat L N PE Heating pump Elect...

Страница 11: ...ler below which the defrosting of the panels stops bmin not set 20 tbH Maximum allowable temperature in the boiler Tbmax 80 100 95 tPL Minimum temperature of solar panels min 20 50 40 tPH Maximum allo...

Страница 12: ...y period is 24 months following the purchase date of the unit or its installation by an authorized Engineering Company but not exceeding 28 months after the production date The warranty is extended to...

Отзывы: