 RT-SVX058C-EN

Start Up

Standard Economizer Start-Up

1. Set the minimum position setpoint for the economizer 

to the required percentage of minimum ventilation 
using the setpoint potentiometer located on the 
Economizer Control (ECA).

The economizer will drive to its minimum position 
setpoint, exhaust fans (if applicable) may start at 
random, and the supply fan will start when the 
SERVICE TEST is initiated.

The Exhaust Fan will start anytime the economizer 
damper position is equal to or greater than the exhaust 
fan setpoint.

2. Verify that the dampers stroked to the minimum 

position.

3. Verify that the dampers stroked to the full open 

position.

4. To stop the SERVICE TEST, turn the main power 

disconnect switch to the “Off” position or proceed to 
the next component start-up procedure. Remove 
electro mechanical test mode connections (if 
applicable).

LLE Controls Test Procedure

See unit schematic for correct wire numbers.

Use the CHECKOUT menu in the Installation Instructions 
to test the damper operation and any configured outputs. 
Only items that are configured are shown in the Checkout 
menu.

To Perform Checkout Tests:

1. Scroll to the desired test in the checkout menu using 

the  

and  

buttons.

2. Press the 

 button to select the item.

3. “RUN?” is displayed.

4. Press 

 to start the test.

5. The unit pauses and then displays “IN PROGRESS”.

6. When the test is complete, “DONE” appears.

7. When all parameters have been tested, press 

 

(Menu Up) to end the test (e.g. turn off the relay).

Notes:

The checkout tests can all be performed at the time of 
installation or any time during the operation of the 
system.

JADE will be in "set up" mode for the first 60 minutes 
after powered. If OA sensor or Sylk Bus device (sensor 
or actuator) is disconnected during the set up mode, 
the JADE will not alarm that failure. The MA sensor is 
a system "critical" sensor, if the MA sensor is removed 
during the set up mode, the JADE will alarm. After 60 
minutes the JADE controller will change to operation 

mode and all components removed or failed will alarm 
in the operation mode.

Upon power up (or after a power outage or brownout), 
the JADE controller module begins a 5 minute power 
up delay before enabling mechanical cooling.

Compressor Start-Up

1. Attach a set of service gauges onto the suction and 

discharge gauge ports for each circuit. Refer to the 
refrigerant circuit illustration in the Service Facts.

Using the Service Test Guide, perform the proper test 
mode connections.

Scroll Compressors

a. Once the compressor has started, verify that the 

rotation is correct. If wired correctly the suction 
pressure should drop and the discharge pressure 
should rise. If a scroll compressor is rotating 
backwards, it will not pump and a loud rattling 
sound can be observed.

b. If the electrical phasing is correct, before 

condemning a compressor, interchange any two 
leads (at the compressor Terminal block) to check 
the internal phasing. Refer to the following 
illustration for the compressor terminal/phase 
identification. Do not allow the compressor to 
operate backwards for more than 5 seconds. 
Operation for a period of time longer than this will 
result in compressor damage. Copeland (Alliance) 
will experience failure also. If the compressor runs 
backward for an extended period, the motor 
winding can overheat and cause the motor winding 
thermostat to open.

Note:

The Copeland SXA scroll compressors for R-410A 
units use Trane OIL00094. Compressor types are 
listed in 

Table 7, p. 26

. The appropriate oil charge is 

listed in 

Table 8, p. 26

.

2. After the compressor and condenser fan have started 

and operated for approximately 30 minutes, observe 
the operating pressures. Compare the operating 

Table 7.

Compressor types

Tonnage

C1

GB*036

SXA031

GB*048

SXA042

GB*060

SXA051

Table 8.

POE Oil recharge amount (fl. oz.)

Model

C1

GB*036

21

GB*048

38

GB*060

38

Содержание GBC036 Series

Страница 1: ...raining Improperly installed adjusted or altered equipment by an unqualified person could result in death or serious injury When working on the equipment observe all precautions in the literature and...

Страница 2: ...in minor or moderate injury It could also be used to alert against unsafe practices NOTICE Indicates a situation that could result in equipment or property damage only accidents WARNING Proper Field W...

Страница 3: ...ed the General Information Troubleshooting and Wiring Diagrams section WARNING Follow EHS Policies Failure to follow instructions below could result in death or serious injury All Ingersoll Rand perso...

Страница 4: ...IYUDC 23 Through the Base Gas Utility Option 24 Pre Start 25 Verifying Proper Air Flow Units with Belt Drive Indoor Fan 25 Electromechanical Controls Test Procedure 25 Start Up 26 Standard Economizer...

Страница 5: ...zer Dry Bulb W Barometric Relief M Downflow Low Leak Economizer Reference Enthalpy W Barometric Relief P Downflow Low Leak Economizer Comparative Enthalpy W Barometric Relief Digit 15 Supply Fan Drive...

Страница 6: ...r Avoidcontactwiththeskinoreyes Wearlong sleeved loose fitting clothing gloves and eye protection Wash clothes separately from other clothing rinse washer thoroughly Operations such as sawing blowing...

Страница 7: ...r prevents the unit from starting for 3 minutes Phase Monitor The Phase Monitor is a three phase line monitor module that protects against phase loss phase reversal and phase unbalance It is intended...

Страница 8: ...ZERO to 400 ppm and the CO2 SPAN to 1600 ppm in the ADVANCED SETUP menu Occupancy Sensor A customer supplied occupancy sensor can also be added to provide damper control based on occupied unoccupied...

Страница 9: ...nomizer airflows or recirculation of hot condenser air Figure 1 Typical installation clearance for single and multiple unit applications END TO END NOTE 2 3 SIDE BY SIDE NOTE 2 NOTE 1 3 0 4 0 5 0 3 0...

Страница 10: ...CH ACCESS GAS CONNECTION Figure 3 Gas electric units front side views 3 5 tons NOTES 1 THRU THE BASE GAS AND ELECTRICAL IS NOT STANDARD ON ALL UNITS 2 VERIFY WEIGHT CONNECTION AND ALL DIMENSION WITH I...

Страница 11: ...Dimensional Data RT SVX058C EN 11 Figure 4 Gas electric units bottom view 3 5 tons Figure 5 Foundation units back view horizontal configuration 3 5 tons SUPPLY RETURN...

Страница 12: ...Dimensional Data 12 RT SVX058C EN Figure 6 Roof curb 3 5 tons SUPPLY RETURN Figure 7 Downflow unit clearance 3 5 tons standard efficiency CLEARANCE CLEARANCE CLEARANCE CLEARANCE UNIT OUTLINE...

Страница 13: ...tons BACK VIEW OF UNIT RIGHT VIEW OF UNIT ECONOMIZER FAN BAROMETRIC RELIEF BAROMETRIC RELIEF Figure 9 Manual damper 3 5 tons MANUAL DAMPER HOOD BACK VIEW OF UNIT RIGHT VIEW OF UNIT FAN NOTE VERIFY WE...

Страница 14: ...B C D Length Width 3 GBC036 574 524 95 111 172 146 42 29 4 GBC048 616 566 110 119 175 162 40 29 5 GBC060 636 586 120 125 174 168 39 28 a Weights are approximate b Weights do not include additional fa...

Страница 15: ...cklist listed below is a summary of the steps required to successfully install a commercial unit This checklist is intended to acquaint the installing personnel with what is required in the installati...

Страница 16: ...connect switch and to the main power terminal block HTB1 in the unit control panel Install proper grounding wires to an earth ground Note All field installed wiring must comply with NEC and applicable...

Страница 17: ...iring is properly sized and installed follow the guidelines outlined below Note All field installed wiring must conform to NEC guidelines as well as state and Local codes Verify that the power supply...

Страница 18: ...s Provide proper grounding for the unit in accordance with local and national codes Optional TBUE Wiring Through the Base Electrical Option Location of the applicable electrical service is illustrated...

Страница 19: ...ductor for the length of the run Note Resistance in excess of 3 ohms per conductor could cause component failure due to insufficient AC voltage supply 3 Be sure to check all loads and conductors for g...

Страница 20: ...e staged gas pressure valve to a negative pressure 3 5 3 5 3 5 Combustion Blower Suction Pressure 1st Stage 0 50 to 0 55 0 50 to 0 55 0 50 to 0 55 Combustion Blower Suction Pressure 2nd Stage 0 65 to...

Страница 21: ...ch or circuit protection switch and remove the phase sequence indicator Compressor Crankcase Heaters Each compressor can be equipped with a crankcase heater The proper operation of the crankcase heate...

Страница 22: ...bearings for sufficient lubrication If the belts require adjustment or if the bearings need lubricating refer to the maintenance section of this manual for instructions Verify that a condensate trap i...

Страница 23: ...low voltage class II control wiring through hole in base of unit but not through high voltage conduit refer to Figure 15 p 18 for high and low volt conduits location Feed control wiring through bushin...

Страница 24: ...dures to ensure the power cannot be inadvertently energized Verify with an appropriate voltmeter that all capacitors have discharged Failure to disconnect power and discharge capacitors before servici...

Страница 25: ...0 using the setpoint potentiometer located on the Economizer Control ECA if applicable Electromechanical Controls Test Procedure See unit schematic for correct wire numbers Fan Test and Minimum Ventil...

Страница 26: ...is a system critical sensor if the MA sensor is removed during the set up mode the JADE will alarm After 60 minutes the JADE controller will change to operation mode and all components removed or fai...

Страница 27: ...ed open the main power disconnect switch to reset the unit Final System Set Up After completing all of the pre start and start up procedures outlined in the previous sections i e operating the unit in...

Страница 28: ...p 28 5 Remove the belt tension gauge The small O ring now indicates a number other than zero on the plunger s force scale This number represents the force in pounds required to give the needed deflec...

Страница 29: ...uperheat For guidelines refer to Compressor Start Up p 26 Note Do NOT release refrigerant to the atmosphere If adding or removing refrigerant is required the service technician must comply with all fe...

Страница 30: ...sprayer nozzle and the microchannel coil is 1 3 Final Process For future reference you may find it helpful to record the unit data requested below in the blanks provided 1 Complete Unit Model Number...

Страница 31: ...lashes on for 1 4 second and off for 1 4 second Call for Heat Continuous On Internal Error Replace Control Board 2 Flashes 1 Hour Lockout No Flame 3 Flashes Pressure Switch Inducer Issue 4 Flashes Ope...

Страница 32: ...not modulating Excess outdoor air The JADE controller is a certified FDD product HJW10 by California Title 24 Part 6 The FDD system is required for meeting California Energy Commission s Title 24 reg...

Страница 33: ...Not OK to Economize Fast Flash 1 4 Second On 2 Seconds Off Error Code Communications Failure Pulse Flash 1 30 Second On 1 4 Second Off 2 Seconds between pulse sequences Error Code 1 Flash Actuator Fa...

Страница 34: ...5 12132103 GBC 036 060 60Hz 1 STAGE Gas Heat 12130803 GBC 036 060 60Hz 2 STAGE Gas Heat Control 208 575 12132965 GBC 036 060 60Hz 1 STAGE Gas Heat 12132966 GBC 036 060 60Hz 2 STAGE Gas Heat Control bo...

Страница 35: ...ited to furnishing F O B Warrantor factory or warehouse replacement parts for Warrantor s products covered under this warranty Warrantor shall not be obligated to pay for the cost of lost refrigerant...

Страница 36: ...and protect food and perishables and increase industrial productivity and efficiency We are a global business committed to a world of sustainable progress and enduring results ingersollrand com Inger...

Отзывы: