Start Up Preparation & Procedures
The following check list shall be adhered to before putting the compressor into operation.
FAILURE TO PERFORM THE CHECKS MAY RESULT IN SERIOUS INJURY OR DEATH, PROPERTY DAMAGE
AND/OR MECHANICAL FAILURE. DISCONNECT AND LOCK OUT POWER SUPPLY.
1. Remove all loose pieces and tools around the compressor installation.
2. Check oil level in crankcase, add as necessary.
3. Check all pressure connections for tightness and leaks.
4. Check to make sure all safety relief valves are in place and operational.
5. Check to be sure all guards are in place and securely mounted.
6. Check fuses, circuit breakers and thermal overloads for proper size.
7. Open all manual shut-off valves (block valves) at and beyond the compressor discharge.
8. On all 3 phase units, after all of the above conditions have been satisfied, jog the starter switch button to check
the rotational direction of the compressor. It should agree with the rotation arrow on the flywheel/pulley (counter
clockwise, facing the shaft).
The following procedures should be followed for start-up of a new installation, or after changes have been made to
an existing installation, and/or after service repair work has been performed.
1. Instructions in addition to those contained within this manual, supplied by manufacturers of supporting
equipment, must also be read and understood before start-up.
2. Check oil level in crankcase.
3. Drain moisture from air receiver and traps.
4. Start compressor and watch for excessive vibration or strange noises. If either is observed, stop the
compressor immediately and correct.
5. Check air receiver or system pressure.
6. Manually activated safety relief valves by pulling ring or lever.
7. Check operation of controls.
8. After two days of operation check belt tension, air piping for leaks, and crankcase oil level.
Industrial Gold Air Compressors
|
800-531-9656 | www.industrialgold.com