8.2 Procedure

 

 

 

Pierce or pull out cable feedthrough (6) and feed connection cable through. 
Check supply voltage. See name plate for allowable voltage. Use shielded 
connection cable to the electrode 2 x 2 STP, e.g. LIHF/GLS, 
 4 x 0.75 mm². 

 

Length of connecting line max. 100 m at 5 – 10,000 µS/cm or max. 30 m at 
0.5 – 2,000 µS/cm. 

 

Only connect shielding on the SMLC1 control unit (terminal 6). After electrical 
connection - with device disconnected from the mains - put hood (7) on 
holder (5) and tighten fastening screws (3). 

 

(see sketch p. 7) 

 
 

8.3 Testing

 

 
Switch on supply voltage, the green LED 

"U

B

 lights up.  

 

 

When the electrode is uncovered the red LED lights up “

FAULT”.

 

 

When the electrode is submerged the LED “

FAULT” 

must not light up. 

 

The LED 

"TEST"

 must light up for one second every two minutes.  

 
A successful test is confirmed by the red LED flashing briefly. 
 
 
 
 
 

9.   Technical data 

 

 
 

9.1 Device data 

 

 

Component 

  TÜV ID: 000006173 

CE ID no.:  0035 
Manufacture in accordance with EC Directive 97/23/EC,  
Modules B+D, Category IV, EC type test W 17/02, 
Applied standards: 
Control device: DIN EN 50081-1, DIN EN 50082-1 
Electrode     TRD, AD2000, ASME boiler 

  230 V ± 15% 

Mains connection 

  50/60 Hz 

Power consumption 

approx. 4.5 VA 

Device fuse 

80 mA/T 

Protection in accordance with DIN VDE 0470 

IP 40*  

Allowable ambient temperature 

0 - 60°C 

* IP 54 protection class is to be ensured in the boiler area to comply with the German regulation 
VdTÜV-Wasserstand 100, 4.90. 

 
 
 
 
 
 
 
 

Содержание SMLC 1

Страница 1: ...Low water level limiter SMLC1 With level electrode EL 030 EL 19 2 D 08 B 16644 1 Edition 07 11 Installation and operating instructions...

Страница 2: ...allation 8 6 Configuration 8 7 Fitting the electrode 9 11 7 1 Fixing elements for receiving electrodes 10 12 7 2 Mounting in mounting housing 12 13 7 3 Adjusting the electrode plugs 14 7 4 Shortening...

Страница 3: ...ese assembly and operating instructions in the relevant language of the country must accompany it Work on the device should only be carried out by trained staff specially commissioned and exclusively...

Страница 4: ...4 Exclusion of liability IGEMA GmbH Mess und Regelsysteme will assume no liability if the above mentioned regulations instructions and safety precautions are not noted and followed...

Страница 5: ...ng the output of the input stage in the rhythm of 40 ms for its in phase dynamic behaviour If the behaviour is correct the timer and control unit activates the driver of the final stage with its own m...

Страница 6: ...er dynamic monitoring the periodic overall test of the device takes place every 2 minutes for one second as a fully automatic process The yellow LED TEST shows that the test is being carried out follo...

Страница 7: ...ng with a spring catch for the DIN EN 50022 standard 35 mm carrier rail and for screw fixing on a mounting plate 4 1 Installation dimensions and descriptions SMLC1 Base Front view Side view with conne...

Страница 8: ...3 mm drill Fit base 5 on base plate with two M4 screws 6 Configuration The preset switch off time can be changed It is to be agreed with the local expert Setting the switch off time Open SMLC1 To do...

Страница 9: ...lectrode shank Screw up both parts by means of the enclosed M4 set screw with SW2 hexagon socket Screwing in the electrode Release screw 1 and pull off electrode plug 2 Clean sealing surfaces and chec...

Страница 10: ...ing to DIN Drilling plans 1 8 Bohrbild means drilling plan Seals according to DIN PN DN DIN Sealing surface Form Threaded hole Material 40 2635 B 63 2636 100 160 50 2638 DIN 2526 E according to drilli...

Страница 11: ...0 x 100 100 160 50 976 4 M24 x 110 1 7709 40 M20 x 90 63 976 M24 x 110 1 7709 100 160 100 2510 8 LM27 x 145 Ck 35 DIN nuts PN DN DIN Numbe r Dimension Material 40 M16 63 M20 100 160 50 EN 24032 8 M24...

Страница 12: ...housing The approval is only valid if shut off valves are mounted between the process connections of the mounting house and the boiler supports and a relief valve is fitted on the mounting housing Il...

Страница 13: ...rocess connection M2 PN DN DIN Sealing form DIN 16 25 40 20 2635 2526 Form C 63 100 2637 160 25 2638 2526 Form E On request ASME compliant flanges weld on ends or DIN or ASME compliant socket welding...

Страница 14: ...d snap in retighten the electrode plug 5 7 4 Shortening the electrode extension see sketch page 9 Never dismantle the electrode when the boiler mounting housing is pressurised Release screw 1 and pull...

Страница 15: ...ing to the wiring diagram illustrated 8 1 Wiring diagram EL 030 EL 19 2 See name plate of supply voltage Safety chain Alarm Power connection Shielded connection line e g LIHF GLS 4 x min 0 75 mm Cable...

Страница 16: ...is uncovered the red LED lights up FAULT When the electrode is submerged the LED FAULT must not light up The LED TEST must light up for one second every two minutes A successful test is confirmed by...

Страница 17: ...osition 800 with protective tube DN 50 vertical installation position 800 with protective tube DN 50 100 installation position inclined up to 45 9 2 Maximum ratings of potential free contacts Safety c...

Страница 18: ...months The condition for this is proper handling in accordance with the assembly and operating instructions For worn and replacement parts the warranty is limited to defects of material and manufactur...

Страница 19: ...ressure accessory Product type Control device SMLC1 with Electrode EL030 or EL19 2 comply with the directives and have been subjected to the following conformity assessment procedure Category IV Modul...

Страница 20: ...the QM System guidelines in accordance with DIN EN ISO 9001 2000 If the device supplied shows transport damage or gives cause for complaint in spite of our final quality control please contact our SER...

Отзывы: