RACK-3200G QIG IEI Technology Corp.
Page 3
INSTALLATION STEPS
To install the RACK-3200G chassis, the following installation steps
must be completed:
Step 1:
Unpack the chassis.
Step 2:
Install the front handles.
Step 3:
Remove the top cover.
Step 4:
Install the rear panel serial port, parallel port and PS/2
connectors.
Step 5:
Install the PSU.
Step 6:
Install the backplane.
Step 7:
Install the CPU card.
Step 8:
Install the PCI and ISA expansion cards.
Step 9:
Install the disk drives.
Step 10:
Front panel cables.
Step 11:
PSU cable and interface cable connections.
Step 12:
Cover reinstallation.
Step 0:
The installation steps outlined above are described in detail below.
Please refer to the relevant section.
STEP 1: UNPACK
The RACK-3200G is shipped in a plastic bag that is placed inside a
cardboard box. The accessories are also shipped with the chassis.
When you unpack the chassis you must:
Make sure all the items listed in the
PACKING LIST
section
above are present.
Make sure the chassis has not been damaged in anyway.
STEP 2: FRONT HANDLE INSTALLATION
Two handles are shipped with the RACK-3200G chassis. The
handles are installed on the sides, at the front of the chassis. Each
handle is secured to the chassis by four retention screws. To install
the handles, please follow the steps below.
Step 1:
Align the retention screw holes on the side of the chassis
with the retention screw holes in the handle.
Step 2:
Insert the retention screws.
Step 0:
Figure 2: Front Handle Retention Screws
STEP 3: REMOVE THE TOP COVER
The top cover of the chassis is secured to the chassis with eight
retention screws, four on each side. To remove the top cover, please
follow the steps below.
Step 1:
Remove all eight top cover retention screws. Remove four
retention screws from each side of the chassis.
Figure 3: Top Cover Retention Screws
Step 2:
Slide the cover backwards and then lift it up gently.
Step 0:
Figure 4: Remove the Top Cover
STEP 4: INSTALL THE REAR PANEL
SERIAL PORT, PARALLEL PORT AND
PS/2 CONNECTORS
The rear panel of the RACK-3200G can accommodate:
o
2 x serial ports
o
3 x parallel ports
o
1 x PS/2 connector
Figure 5:
Parallel Port and Serial Port Locations
These ports must be installed before any other components are
installed. To install these connectors please follow the steps below.
Step 1:
Snap off the port covers in accordance with the number
and type of ports you need.