SmartCAFS Mixing Manifold
Manifold should be mounted with provision for drainage.
Foam and air injection points identified above.
By-Pass Valve
This valve is adjusted to give the required dry foam flow-rate - typically 100 litres/minute.
To set the required dry foam constituency
–
1. Install the system as directed
2. Run the system at normal operating pressure, discharge compressed air foam through the
most restrictive line, typically a hose reel.
3. Set the SmartCAFS ARC control to the full dry position.
4. Open or close the By-pass valve (as shown in photograph above) until the required dry
foam flow rate is achieved.
5. Remove the By-pass valve lever so this setting cannot be changed in operation.
By-pass valve lever
for setting dry foam
consistency
Air injection
point
3” Victaulic
connection
(Both ends, not
shown)
Water flow
Foam injection
Flow sensor
Wet/dry foam setting valve