Proof of Performance

1. Connect the PL adapter to the main 

handset and channel adapter to the 

remote. 
Highlight the copper test icon and 
press ENTER.

Note: Current test standard shown in 
red circle.

Setup:

 Configuring MPTL tests

5. Enter a known NVP value for the 

cable and press ENTER;  
or  
press F3 (Meas NVP) to calculate the 

NVP for a known length of cable.

3. Highlight Twisted Pair Perm and 

press ENTER.

6. MPTL is configured and ready to test. 

The current test standard line will 

update to display the newly selected 
standard.

2. Highlight TIA or ISO and press 

ENTER.

4a (TIA). Highlight Cat 6A MPTL (UTP 

or STP) and press ENTER. 

4b (ISO). Highlight ISO Ea PL2/PL3 

MPTL (UTP or STP) and press ENTER. 

TIA application note

MPTL is defined in the ANSI/TIA-568.2-D standard that 
was not ratified when LanTEK software version 3.200 
was released.

The pass/fail criterion for MPTL is identical to the 
Permanent Link test limits. While there is no expectation 
that the specifications for MPTL will change; version 
3.200 is testing to a draft standard.

ISO application note

MPTL is not currently specified by ISO, though a task 
group in ISO/IEC-SC25/Working Group 3 is working to 
specify MPTL.

ISO and TIA actively work to make new specifications 
common. Due to customer demand, and the expectation 
that ISO will adopt MPTL, it has been added to LanTEK 
version 3.200 software. 

Use the TIA cat 6A MPTL selection if testing MPTL 
cabling configurations to a current standard document 
is required.