Installing a BAX® System Q7 Guide  

New Q7 & Swap 

 

Pre-installation Site Requirements

 

 

(Email the instrument specifications from BAX® User Guide prior to Visit): 

100-240 VAC ±10%, 50/60 Hz ±1%, 15 Amp circuit; if this is uncertain an Uninterruptible Power 
Supply (UPS) will be needed – APC 2200 or equivalent recommended.  

It is also recommended to have a surge protected power strip with line filtering to protect the system 
– APC SurgeArrest recommended. 

3 outlets (monitor, computer, cycler/detector) 

Benchtop able to support 54.5 kg (120 lbs) 

Unpacking and Installation 

1.  Check the shipping containers for damage, if noted take photos to document damage. Open 

the box by prying out the black plastic pegs on each corner, remove grey corner caps, take 
off the sides of the box to remove the unit.  

2.  The instrument is heavy and may require two people to lift.  Use a cart if needed to transport 

into laboratory area.   Place the BAX® System Q7 on a stable bench/countertop. Confirm 
that the serial number matches the paperwork.   

a.  Leave 15 cm (6 in.) between the instrument and wall. Connect the instrument to the 

CPU via USB cord and connect to outlet, set up CPU and monitor, and power on the 
system. (More detailed instructions can be found in the BAX® System Q7 User’s 
Guide). 

i.  Note: There are four cables to connect: 

1.  Mouse (USB port 

2.  Keyboard (USB port) 

3.  Communication cable (between the cycler and the computer, 

tan/white color) 

4.  Display cable between the monitor and the computer (DPI, HDMI, 

VGA) 