INSTALLATION MANUAL
MASTERLINE Ultimate Micro
Page 4 of 4
HUBER+SUHNER disclaims any liability resulting from incorrect installation and use, including any damages resulting from the use of tools and
accessories other than the ones recommended herein. Any installation performed by unqualified personnel voids the product warranty provided by
HUBER+SUHNER. All due care and attention must be exercised when performing the installation of these products. For advice concerning the gen-
eral handling of these products please contact HUBER+SUHNER.
Step 6:
Use jumper cables to connect the MLUM sys-
tem to the RRH. The connectors can be en-
gaged in the available ports by applying gentle
pressure. Turn the connector in the opposite
direction to check that it is properly engaged.
Please refer to the general instructions in the
user manual for guidance on handling cables
and laying multi-connector cables.
Step 7:
All jumper cables must be secured according
to national and local regulations. The weight of
the cable must be supported by the cable fas-
teners.
Step 8:
Once all the jumper cables have been con-
nected, the main feed can be connected to the
base station or another signal source.
The protective tube must be removed before
connecting.
When untwisting the protective tube, ensure
that the cable is not twisted around its own
axis.
Step 9:
Connect the MLUM housing to the base sta-
tion using suitable cables.
The connectors can be engaged in the ports
provided by applying gentle pressure. Turn the
connector in the opposite direction to check
that it is properly engaged.
Please refer to the general instructions in the
user manual for guidance on handling cables
and laying multi-connector cables.
REVISION HISTORY
Revision
Description of detailed changes
Manager/Engineer
Applicable
date
Rev. A
First Version
David Neher
2020-07-06