Screw

O-Ring

Backplate

Cover

INSTALLATION

OPERATION

120VAC
(black 
and 
white 
wires)

Connect both black transformer and 

heater harness wires to hot (120V) 

wire from building. (Separately cap off 

transformer red wire and heater harness 

red wire).

277VAC
(red and 
white 
wires)

Connect both red transformer and 

heater harness wires to hot (277V) wire 

from building. (Separately cap off trans-

former black wire and heater harness 

black wire).

Ground

Connect ground (green) conductor.

IMPORTANT:

Once unit is connected and cover is snapped onto backplate, gently 

seat screws onto O-ring seals to less than 1/2FT-LB (.7N-m).

DO NOT OVERTIGHTEN!

O-RING MAY BE DAMAGED AND THE UNIT WILL LEAK IF ABOVE 

IS NOT FOLLOWED.

1.Open the unit by loosening both screws on top of unit until screws spin 

freely.  Pry cover from backplate, and remove cover squarely from 

backplate.  (Remove screws prior to re-installing cover.)

2.Remove 7/8” diameter K.O. from backplate if mounting 

to electrical box or  remove 1/2”-1/4NPT pipe plug if 

using conduit.

CONDUIT MOUNTING:

If unit is not secured to mounting surface using 

unit backplate K.O. pattern and supplied gasket, 

use sealant to create waterproof seal between the 

mounting surface and the unit backplate. 

IMPORTANT!

To weatherproof your outdoor installation, be sure to 

seal all fixture openings - mounting, conduit, etc.

4.Peel backing from J-Box Gasket and 

adhere to backplate around center K.O.

5.Feed building wires through 

center K.O. as shown and 

  secure backplate using 

screws supplied with 

  electrical box.

3.Remove appropriate backplate 

K.O.’s for electrical box screws.

6.Connect building wires to 

transformer and heater 

harness (if supplied).

7.Connect heater harness 

to heater/battery pack as 

shown (if supplied).

8.Connect battery wiring to 

charger PCB as shown.  

NOTE:  Connecting battery 

will turn emergency lights 

on.  Press test switch to turn 

lights off. 

NOTE:  Feed wires and wire nuts back into electrical 

box through backplate as shown.

9.Connect transformer 

secondary wiring to charger 

PCB as shown.

93021938

93022008

93022006

93022007

7/8” Dia. K.O.

Building 

Ground 

Wire

Heater Harness

(if supplied)

Transformer

Secondary

Winding

10.Attach unit cover to 

  backplate by reversing 

Step 1.  Ensure all wires 

are within enclosure to 

avoid pinching with cover.

WARNING:  DO NOT jOIN UNUSED WIRING - 
CAP OFF UNUSED WIRES INDIVIDUALLY.

Path for AC Heater 

Harness & Transformer

Primary Wiring

Heater/Battery Pack

Charger PCB

All models are provided with the Dual-Lite Spectron self-testing/self-diagnostic electronics 

system providing:

 

Visual indication of AC power status

 

Visual indication of all self-diagnostic test cycles

 

Visual indication of unit malfunctions including:

 

 

Battery fault

 

 

Charger fault

 

 

Transfer Fault

 

 

Lamp fault

Bi-Color LED Status Indicator

Self-testing/self-diagnostic units are provided with a single, bi-color LED which serves as a com-

bination AC power, self-test and service alert status indicator. During normal operation, the green 

status LED will be constantly illuminated, indicating the presence of AC power. During all automatic 

or manual self-test cycles, the green Status LED will blink at a one cycle per second rate indicating 

“Test In Progress". If a fault condition is detected during any automatic or manual self-test cycle, upon 

completion of test the red status indicator will provide a “service alert code” – see table below.

Spectron® Self-Testing/Self-Diagnostic Model

Service Alert Code

Description

One blink ON/pause

Battery not connected

Two blinks ON/pause

Battery fault

Three blinks ON/pause

Charger fault

Four blinks ON/pause

Transfer circuit fault

Five blinks ON/pause

Lamp failure

Manual Test
Using the unit test switch, users can initiate different duration test cycles based on the following table:

To Initiate Action:

Test Cycle

Press switch once

1 minute

Press switch twice

90 minute

Pressing test switch at any time after a test cycle has begun cancels the remainder of test and returns 

the unit to normal operation. 

(NOTE: Batteries are often shipped in a discharged state – this is normal 

– battery requires charging. Allow several hours of charge before testing unit.)

 

LEDs produce heat – use CAUTION around LED assembly.
SPECTRON units also provide:

Brownout protection – unit transfer to emergency mode with low AC input voltage.

Time Delay Re-transfer – unit will remain in emergency mode for additional time after AC power 

is restored.

1/2”-14NPT
Pipe Plug