Figure 6-187 Installing rectifiers and baffle plates
----End
6.4.4.3 Installing Cables
Procedure
Step 1 Install cables by referring to Single UPS Installation (1200 kVA, Three-Phase
Three-Wire) > Installation in Standard Configuration > Installing Cables.
Step 2 Remove the front cover from the UPS.
Step 3 Remove an accessory cover from the top of the top air-flow cabinet.
Step 4 Connect the power cable to the 380~480V System port on the UPS and the signal
cable to the XS2 port.
UPS5000-H-(1200 kVA-1600 kVA)
User Manual (100 kVA Power Modules)
6 Installation
Issue 05 (2021-10-13)
Copyright © Huawei Technologies Co., Ltd.
195