Follow-up Procedure
After connecting cables, reinstall the covers of the power distribution subrack, rear panel,
and side panel of the bypass cabinet.
After connecting cables, check that a certain clearance is reserved between the internal
switch (if any) extension pole and power cables to avoid friction.
3.2.7 Routing Cables (800 kVA UPS)
3.2.7.1 Top Cable Routing
Context
Route cables for the UPS from inside out and from top down.
This section introduces the dual mains scenario. If single mains is used, you do not need to
remove the copper bars between the mains and bypass input terminals or connect the
bypass input cable.
The figures are for reference only. For more information about the recommended cable
cross-sectional area and quantity, refer to