5 Operations
Issue 02 (2020-01-10)
Copyright © Huawei Technologies Co., Ltd.
150
After the inverter starts, the UPS still works in bypass mode and the inverter is on standby.
shows the power flow displayed on the
System Status
screen. If the bypass is not
normal, the inverter supplies power immediately. If the inverter is not started, the UPS may be
disconnected.
Figure 5-15
System Status screen
----End
5.6 Testing Batteries
5.6.1 Forced Equalized Charging Test
Context
Before a forced equalized charging test, ensure that:
The mains input is normal.
Batteries are properly connected.
Batteries are not in the equalized charging state.
Procedure
Step 1
On the home screen of the LCD, choose
System Info
>
Maintenance
>
Battery Maint
.
Step 2
Tap
Start
next to
Forced Equalized Charging
to start a forced equalized charging test.