![Huawei TaiShan 2280 V2 Скачать руководство пользователя страница 66](http://html.mh-extra.com/html/huawei/taishan-2280-v2/taishan-2280-v2_user-manual_169709066.webp)
Figure 4-4
Installing an L-shaped guide rail
3.
Install the other guide rail in the same way.
Step 3
Install the server.
1.
Lift the server. This task requires at least two people.
2.
Place the server on the guide rails and slide it into the cabinet. See (1) in
.
Figure 4-5
Installing the server
3.
When the two mounting ears of the server come into contact with the mounting bars on
the cabinet, tighten their captive screws to secure the server. See (2) in
.
TaiShan 2280 V2 Server
User Guide
4 Setup
Issue 01 (2019-07-01)
Copyright © Huawei Technologies Co., Ltd.
58