7 Hoisting an RRU and Related Cables onto a Tower
Issue Draft B (2018-05-15)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
41
Figure 7-4
Incorrect binding method (2)
Step 6
Hoist the RRU onto the tower, as shown in Figure 7-5. Installation engineer B pulls the lifting
sling downwards, and installation engineer C pulls the traction sling outwards to protect the
RRU from colliding with the tower.