6
Powering On and Off the RH8100 V3
About This Chapter
This topic describes the precautions and procedures for powering on and off the
RH8100 V3.
6.1 Powering On the RH8100 V3
6.2 Powering Off the RH8100 V3
6.1 Powering On the RH8100 V3
This topic describes how to power on the RH8100 V3.
Scenarios
●
The RH8100 V3 needs to be powered on after it is properly installed.
●
The RH8100 V3 needs to be powered on after it is maintained.
The method for powering on the RH8100 V3 varies according to the scenario.
Prerequisites
Conditions
●
The RH8100 V3 and its internal components are properly installed.
●
The server is properly grounded.
Data
●
You have determined the cabinet number and installation position for the
RH8100 V3 to be powered on.
●
You have obtained the IP address, user name, and password for the iBMC
management network port.
Tools
ESD wrist strap or ESD gloves: used to prevent ESD damage
Documents
RH8100 V3 Server
User Guide
6 Powering On and Off the RH8100 V3