4 Commissioning
Issue 06 (2020-01-13)
Copyright © Huawei Technologies Co., Ltd.
156
Figure 4-25
Fan commissioning
The fan commissioning item is mandatory. After commissioning for a component succeeds, the system
automatically performs commissioning for the next component you selected. If commissioning fails,
startup wizard ends.
Step 6
View the commissioning result.
is displayed if component commissioning succeeds.
Figure 4-26
Commissioning successfully
is displayed if component commissioning fails, which ends startup wizard
commissioning.