FusionModule5000 Smart Modular Data Center
Installation Guide (Single-Row Aisle Containment with
2000 mm High Cabinets, ECC800)
5 Installing the Cabinet
Issue 01 (2019-03-05)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
71
Figure 5-9
Taking out PDU2000 industrial connectors
Step 2
Lay out the PDU2000 industrial connectors and cables on the cabinet top, and reinstall the
rodent-proof mesh, as shown in
Cut the rodent-proof mesh based on the cable thickness using diagonal pliers. If the opening is
too large, unwanted things may fall into the cabinet through the opening.
Figure 5-10
Laying out PDU2000 industrial connectors and cables
Repeat the preceding steps to take out and preinstall PDU2000 industrial connectors for all cabinets.
----End